Verifying a successful installation 51
ATTENTION
The red fan tray fail LED may light briefly while the fans power to operational speed.
--End--
LED power supply
After you turn on the Ethernet Routing Switch 8000 Series, each module automatically initiates a diagnostic test to verify proper module function.
If the power supply LED remains off, do the following:
Procedure steps
Step Action
1Turn the power switch on each power supply to the off position.
2Wait 1 minute.
3Turn the power switch on each power supply to the on position.
--End--
Verifying a successful installation
•The following list describes a successful starting sequence for an Ethernet Routing Switch.
—When power is applied to the Ethernet Routing Switch 8000, the green LED on each power supply and fan tray or cooling module turns on, and the Online LED for each module is amber.
—Each module initiates a
—Upon successful completion of the
—After 1 minute of operation, the fan tray Pass LED lights remain green.
—If the LEDs on the modules light in this sequence, your installation is successful. Contact your network administrator to verify that the Ethernet Routing Switch 8000 is connected to the network.