Chapter 6-Reservations
6-2
System resources are calculated according to the RMX’s license. For
more information see "Video/Voice Port Configuration” on page16-39.
System resource availability is partially checked when reservations
are created:
If a conference duration extension request is received from an
ongoing conference, the request is rejected if it would cause a
resource conflict.
If several reservations are scheduled to be activated at the same
time and there are not enough resources for all participants to be
connected:
The conferences are activated.
Participants are connected to all the ongoing conferences
until all system resources are used up.
If sufficient resources are not available in the system and a scheduled
Reservation cannot be activated, the Reservation is deleted from the
schedule.
Resources for Reservations are calculated using the Reserve Resources
for Audio/Video Participants fields of the New Reservation dialog box.
For more information see "New Reservation – Reserved Resources” on
page6-12.
Resources are reserved for participants at the highest video
resolution supported by the Line Rate specified in the conference
Profile and up to the maximum system video resolution specified by
the MAX_CP_RESOLUTION system flag.
If the RMX is in MPM+ Mode and Fixed Capacity Mode is selected, the
number of resources allocated to this type of video participant (CIF,
SD, HD) is also checked. If resource deficiencies are found an error
message is displayed.
When a new Reservation is created in the Reservations, the effect of the
new Reservation (including its recurrences) on available resources is
checked. If resource deficiencies are found an error message is
displayed.
Defined dial-in or dial-out participants, Meeting Rooms, Entry
Queues and new connections to Ongoing conferences are not
included in the resources calculation.