1 - INSTALLATION AND COMMISSIONING
1.3 - Connecting ports
The connections to be performed on the equipment depend on the configuration chosen:
On the power supply card:
poser supply ports: "PWR" or "PWRA" and/or "PWRB",
On the subrack motherboard strip:
management ports : "COMM", "ETH" and/or "MNGT"
Remote indication, remote control and station alarm port : "LOOPS"
2Mbit/s G.703 synchronization port : "SYNC"
21x2Mbit/s G.703 traffic ports: "E1 INPUT" and "E1 OUTPUT".
Depending on the traffic modules used
optical
SEthernet port
21x2Mbit/s G.703 traffic ports.
Connection requirements :
For a right distribution of cords on either side of the subrack, the connections of slots A and C, the 21 2Mbit/s accesses and synchronization access are oriented leftward. All other
÷connections are oriented leftward.
The run of cords must not hinder the extraction of a module; in particular, connecting cables of the left subrack half is to be secured to the frame with enough backlash to enable the ventilation module to be extracted during a maintenance operation.
1.3.1- Connecting Power Supply
"PWRA" and/or "PWRB" ports, when the equipment is powered from one or two 48 V
Ssources, the power source(s) should be limited to 100 VA.
. "PWR" port when the equipment is powered from a mains voltage (230 V AC), via an optional
Observe the following connection requirements :
"PWR" and "PWRA" and/or "PWRB" Power supply ports can be connected simultaneously.
The power cord or the
÷source prior to being connected to the equipment.
The
Installation and User Guide - N56717020101
Page | No reproduction or communication without the written consent of SAGEM SA |