1 - INSTALLATION AND COMMISSIONING
LOCAL TEST
*case of underequipped unitary equipment
Equipment Inventory
-48 V power Check
Aggregate optical loopback
Insertion of communication parameters (VT100)
Setting to time and insertion of the test configuration tributary accesses
(HTTP browser)
Tributary Ports continuity check
- 48 V redundancy Check
A and B loops and alarms check
Local transmission test (30 mn) *
Optical connection
Connection of external sync input from of an "Master" equipment
(optional)
Configuration Elaboration
no | Local Test on network | |
| ||
| of last équipment ? | |
|
| yes |
|
| |
|
|
|
| Link established |
Optical measurements
MSP protection check
Counters reset
24 H link Performance
Equipment operational
(constitution of installation file)
Configuration Save
Figure 1-8 – Commissioning procedure for ADR155C network