1 - INSTALLATION AND COMMISSIONING
Installation and User Guide - N56717020101
No reproduction or communication without the written consent of
SAGEM SA

Page A1-19

Equipment Inven tory
- 48 V power Check
Aggregate optical loopback

LOCAL TEST

Local Test on network
of last équipment ?
no
Link established
Optical measurements
MSP protection check
24 H link Perform ance
Counters reset
Equipment operati onal
(constitution of installation file)
Tributary Ports continuity check
A and B loops and alarms check
Local transmission test (30 mn) *
Optical connection
Connection of external sync input from of an "Master" equipment
(optional)
Configuration Elaboration
- 48 V redundancy Check
yes
Insertion of communication parameters (VT100)
Setting to time and insertion of the test configuration tributary accesses
(HTTP browser)
* case of underequipped
unitary equipment
Configuration Save
Figure 1-8 – Commissioning procedure for ADR155C network