4 Replacement Procedures

4.6 Switch membrane

Installing the switch membrane

The following describes the procedure for installing the switch membrane (See Figure 4-11).

1.Connect the switch membrane to the connector CN9650 on the system board.

2.Slide the switch membrane to install and secure it with the following screw.

? M2.5? 2.8B FLAT BIND screw

x1

3. Install the LCD CON holder and secure it with the following screw.

? M2.5? 6B

FLAT BIND screw

x1

NOTE: When installing the LCD CON holder, be careful not to catch harnesses, cables and the core of the LCD harness.

QOSMIO F10 Maintenance Manual (960-498)

4-23

Page 255
Image 255
Toshiba qosmio f10 manual Replacement Procedures Switch membrane, Installing the switch membrane