American Power Conversion 250 A Installation, Total power off procedure, Operating environment

Page 13

Warnings

Installation

For complete installation instructions, refer to the Electrical Installation Manual.

See also

Install the ATS in accordance with the National Electrical Code (NFPA 75) in the United States, or in accordance with the Canadian Electrical Code (CSA C22.1-02) in Canada.

When connecting Source 1 power to the ATS, install an external circuit breaker to protect against over-current conditions. The external circuit breaker must be rated at 250 A, with a symmetrical ampere rating of 35,000 rms.

Total power off procedure

To reduce the risk of electric shock or injury to personnel, disconnect all sources of power supply before servicing. To disconnect all sources of supply, follow this procedure:

1.Set the Automatic Operation switch on the dead front of the ATS to Disable.

2.Set the Source 1 switch on the ATS to OFF.

3.Set the Source 2 switch on the ATS to OFF.

4.Set the main Source 1 circuit breaker to OFF.

5.Set the main Source 2 circuit breaker to OFF.

6.If Source 2 is a generator, set the generator control switch to OFF. If OFF is not an option, set the generator control switch to Manual.

Operating environment

The ATS is designed for indoor use only; protect from water and conductive contaminants.

Temperature: 23 to 104°F (–5 to 40°C)

Humidity: 0–95%, non-condensing

Elevation:

6,562 ft (2000 m)

InfraStruXure Power Generation System

3

Image 13
Contents Operation Page About This Manual How to find updates to this manualAudience Companion manualsPage Contents Display Interface Communication Configuration Customizing and Updating the ATS Specifications Page Cross-reference symbols used in this manual Safety symbols used in this manualOverview Wire sizing Total power off procedure InstallationOperating environment Page Overview InfraStruXure Power Generation SystemSystem Operates How the InfraStruXure Power GenerationGenerator cool-down Generator start sequenceOpen and closed transfers Fuel monitoring/runtime calculation Page Front view, door closed Smart Distribution Panel with ATS The automatic operation Control panel is used to set Front view, door openATS panel board, left side Installation Manual for instructionsATS panel board, right side ATS Component Details Motorized switchesUser connection plate Automatic operation control panelATS monitoring unit  When the EPO Arm/Test rocker is in the TestATS label kit Automatic Operation OperationAutomatic Operation Problem-loss of automatic operation Emergency Manual Operation Set the ATS Automatic Operation switch to Disable How to power the load from the generatorEmergency Manual Operation How to return to powering the load from utility Press Total Power Off Total Power Off Display Interface Top-level menu screen Top-level status screensNavigating through screens Password-protected screensPower Factor Total Load by PhaseLoad-Meter Total Load SummaryATS Position ATS/VoltageS1-Utility S2-Generator ATS Setup ATS/Voltage Generator Status GeneratorGen Output Adjust Operating SettingsManufacturer Data View Test Log TestingRun/View Test Test Duration Test ScheduleHow a test occurs Reset All ResetStats View Active Alarms AlarmsAlarm/Event Log Alarm SetupClearing latched alarms Alarm BeeperFuel Alarm Limits Other LimitsSystem Password ConfigSystem/Network Date/TimePage Factory Defaults Electrical ConfigFirmware Updates Reset 100% Fuel LevelPage Overview ATS Management OptionsInfraStruXure Manager Network management interfacesConnect the ATS to the InfraStruXure Manager Configuring the InfraStruXure ManagerConnect the ATS to your network Configuring the ATS Network Management InterfaceTCP/IP configuration methods Configuration overviewDevice IP Configuration Wizard Bootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Remote access to the control console Local access to the control consoleChoose Network from the Control Console menu Control consoleWeb interface How to Access the ATS Network Management InterfaceSnmp Telnet and SSHFTP and SCP InfraStruXure Power Generation System Customizing and Updating the ATS How to connect contacts to the user interface board EPO Test NC no How to Connect an EPO Switch to the ATSContact Closure-Normally Open Problem Action Safety warnings How to Allow Easy Access to the ATS Display Interface Part Number Description Height on Panel Output distribution circuit breakers available from APCCircuit breaker adapter modules available from APC Determine the configuration of the panelCombination #1 Allowed circuit breaker combinationsCombination #6 T1 three-pole breaker requires no additional preparation Preparing the breakers for installationT1 three-pole breaker assembly Parts and tools needed for installation proceduresInstalling breakers on the ATS panel bus See also From a local computer How to Download Firmware UpdatesPhysical ElectricalAWG Installation and Wiring 208V 480VCompliance EnvironmentalPage If Source 2 is a Second Utility Appendix Custom InstallationsInfraStruXure Power Generation System Index InfraStruXure Power Generation System InfraStruXure Power Generation System Page Page Page Radio Frequency Interference 990-1845C