American Power Conversion 250 A manual How a test occurs

Page 51
ATS Waiting to Test
Scheduled or Manual Test Initiated
ATS Test
Countdown
Countdown Expires
Generator
Cranking
Source 2 is Good
ATS Test
Warm-Up
Warm-up Time Expires
Load Test?
Yes
Test ATS
With Load Loaded time expires
Unloaded
Test
Unloaded time expires
Generator
Stopping

Testing

How a test occurs

When a test is not in progress, the ATS waits for a test to occur. Initiate a test by scheduling one using the Test Schedule screen on the display interface, or by starting a test immediately through the Run/View Test screen. Once you have initiated a test, the ATS starts counting down until the next test will begin (the Next Test item on the Test Schedule menu). Once the Next Test time expires, the ATS will signal the generator to start. The generator will then crank in an attempt to start. If the generator does not start, the test fails and the ATS logs that the test failed. If the generator starts, and the ATS determines that Source 2 is OK, the test will begin with the configurable Warm Up time. Once the Warm Up time expires, the ATS determines whether or not you want to perform a System Load Test. This is a test the generator runs with the data center load applied.

Log

Test

Failed

Log

Test

Passed

No

If the test does not include a System Load Test, the ATS proceeds to the unloaded test

stage. If the test includes a System Load Test, the ATS transfers to Source 2. The transfer can be open or closed, depending on how the Allow Closed setting is configured on the ATS Setup menu. The load test occurs for the length of the Loaded time and, once the loaded time expires, the ATS will retransfer to Source 1 and then proceed to the unloaded test stage.

During the unloaded test stage, the generator runs for the duration of the configurable Unloaded Test time. Once the Unloaded Test time expires, the generator stops and the ATS logs either that the test was successful or that it failed. The ATS displays test results on the View Test Log menu on the Testing screen.

InfraStruXure Power Generation System

41

Image 51
Contents Operation Page Companion manuals How to find updates to this manualAbout This Manual AudiencePage Contents Display Interface Communication Configuration Customizing and Updating the ATS Specifications Page Safety symbols used in this manual Cross-reference symbols used in this manualOverview Wire sizing Installation Total power off procedureOperating environment Page Overview InfraStruXure Power Generation SystemSystem Operates How the InfraStruXure Power GenerationGenerator cool-down Generator start sequenceOpen and closed transfers Fuel monitoring/runtime calculation Page Front view, door closed Smart Distribution Panel with ATS The automatic operation Control panel is used to set Front view, door openATS panel board, left side Installation Manual for instructionsATS panel board, right side ATS Component Details Motorized switchesUser connection plate Automatic operation control panelATS monitoring unit  When the EPO Arm/Test rocker is in the TestATS label kit Automatic Operation OperationAutomatic Operation Problem-loss of automatic operation Emergency Manual Operation Set the ATS Automatic Operation switch to Disable How to power the load from the generatorEmergency Manual Operation How to return to powering the load from utility Press Total Power Off Total Power Off Display Interface Top-level menu screen Top-level status screensNavigating through screens Password-protected screensTotal Load Summary Total Load by PhasePower Factor Load-MeterATS/Voltage ATS PositionS1-Utility S2-Generator ATS Setup ATS/Voltage Generator Status GeneratorOperating Settings Gen Output AdjustManufacturer Data Testing View Test LogRun/View Test Test Duration Test ScheduleHow a test occurs Reset Reset AllStats Alarm Setup AlarmsView Active Alarms Alarm/Event LogOther Limits Alarm BeeperClearing latched alarms Fuel Alarm LimitsDate/Time ConfigSystem Password System/NetworkPage Reset 100% Fuel Level Electrical ConfigFactory Defaults Firmware UpdatesPage Network management interfaces ATS Management OptionsOverview InfraStruXure ManagerConnect the ATS to the InfraStruXure Manager Configuring the InfraStruXure ManagerConnect the ATS to your network Configuring the ATS Network Management InterfaceConfiguration overview TCP/IP configuration methodsDevice IP Configuration Wizard Bootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Remote access to the control console Local access to the control consoleChoose Network from the Control Console menu Control consoleWeb interface How to Access the ATS Network Management InterfaceSnmp Telnet and SSHFTP and SCP InfraStruXure Power Generation System Customizing and Updating the ATS How to connect contacts to the user interface board EPO Test NC no How to Connect an EPO Switch to the ATSContact Closure-Normally Open Problem Action Safety warnings How to Allow Easy Access to the ATS Display Interface Part Number Description Height on Panel Output distribution circuit breakers available from APCCircuit breaker adapter modules available from APC Determine the configuration of the panelCombination #1 Allowed circuit breaker combinationsCombination #6 T1 three-pole breaker requires no additional preparation Preparing the breakers for installationT1 three-pole breaker assembly Parts and tools needed for installation proceduresInstalling breakers on the ATS panel bus See also From a local computer How to Download Firmware UpdatesPhysical ElectricalAWG Installation and Wiring 208V 480VCompliance EnvironmentalPage If Source 2 is a Second Utility Appendix Custom InstallationsInfraStruXure Power Generation System Index InfraStruXure Power Generation System InfraStruXure Power Generation System Page Page Page Radio Frequency Interference 990-1845C