How the InfraStruXure Power Generation System Operates
Generator start sequence
The generator start sequence is followed only if the Crank setting in the Operating Settings menu on the Generator Settings screen on the ATS display interface is set to Yes. If enabled, the following sequence will occur:
After a start signal is initiated, either by the ATS or manually, and the generator battery is good, the generator engine will crank and the generator should start. If the generator does not start, it will crank for the length of the Crank Time, and then rest for the length of the Rest Time. The generator will repeat this pattern for the number of times set in Crank Cycles before discontinuing further attempts to start. Check the messages on the display interface for reasons why the generator did not start.
On the generator controller interface, the LEDs track conditions during the start sequence:
LED Behavior on the Generator Controller Interface
Start sequence initiated: Generator Started: | Generator Failed to Start: | |||
|
|
|
|
|
Generator cool-down
After the generator has finished powering the load and utility power has been restored, the generator will enter a