American Power Conversion 250 A manual ATS/Voltage, ATS Position, S1-Utility

Page 43

ATS/Voltage

ATS Position: S1

S1-Utility: OK

S2-Generator: OFF

ATS Setup

ATS Position

One of the following options is displayed to describe the selected source:

S1

The Source 1 switch is ON (closed). Source 1 is connected to the output.

S2

The Source 2 switch is ON (closed). Source 2 is connected to the output.

NEUT

The Source 1 and Source 2 switches are OFF (open). Neither source is connected to the output.

S1&S2!

The Source 1 and Source 2 switches are ON (closed). This is an alarm condition.

S1-Utility

One of the following is displayed to describe the condition of the input from Source 1.

OK

Source 1 is acceptable, as defined in the Transfer Points menu (see page 35).

BAD

Source 1 is not acceptable, as defined in the Transfer Points menu (see page 35).

Press ENTER when the selector arrow rests at the S1-Utilityitem to display the following:

L1-2,L2-3,L3-1The Source 1 line-to-line input voltage.

L1, L2, L3 The Source 1 line-to-neutral input voltage. These readings are only displayed on Wye systems.

Frequency The frequency of the utility input, in hertz (Hz).

Qual Describes the quality of the input from Source 1. One of the following conditions is displayed:

Source Good: The source is acceptable, as defined in the Transfer Points menu.

Low Voltage: The input voltage is below the configured Low voltage Transfer Point on one or more of the phases.

High Voltage: The input voltage exceeds the configured High voltage Transfer Point on one or more of the phases.

Phase Imbalance: The percent voltage difference between two phases, as defined by the Phase Balance setting in the Transfer Points menu, has been exceeded.

Freq Range: The frequency is outside the configured Freq range, as defined in the Transfer Points menu.

Bad Rotation: The phase rotation does not match the configured Phase Sequence, as defined in the Transfer Points menu.

Phase Sequence Lists the phase rotation (e.g., A-B-C) of the Source 1 input.

InfraStruXure Power Generation System

33

Image 43
Contents Operation Page Companion manuals How to find updates to this manualAbout This Manual AudiencePage Contents Display Interface Communication Configuration Customizing and Updating the ATS Specifications Page Cross-reference symbols used in this manual Safety symbols used in this manualOverview Wire sizing Total power off procedure InstallationOperating environment Page Overview InfraStruXure Power Generation SystemSystem Operates How the InfraStruXure Power GenerationGenerator cool-down Generator start sequenceOpen and closed transfers Fuel monitoring/runtime calculation Page Front view, door closed Smart Distribution Panel with ATS The automatic operation Control panel is used to set Front view, door openATS panel board, left side Installation Manual for instructionsATS panel board, right side ATS Component Details Motorized switchesUser connection plate Automatic operation control panelATS monitoring unit  When the EPO Arm/Test rocker is in the TestATS label kit Automatic Operation OperationAutomatic Operation Problem-loss of automatic operation Emergency Manual Operation Set the ATS Automatic Operation switch to Disable How to power the load from the generatorEmergency Manual Operation How to return to powering the load from utility Press Total Power Off Total Power Off Display Interface Top-level menu screen Top-level status screensNavigating through screens Password-protected screensTotal Load Summary Total Load by PhasePower Factor Load-MeterATS Position ATS/VoltageS1-Utility S2-Generator ATS Setup ATS/Voltage Generator Status GeneratorGen Output Adjust Operating SettingsManufacturer Data View Test Log TestingRun/View Test Test Duration Test ScheduleHow a test occurs Reset All ResetStats Alarm Setup AlarmsView Active Alarms Alarm/Event LogOther Limits Alarm BeeperClearing latched alarms Fuel Alarm LimitsDate/Time ConfigSystem Password System/NetworkPage Reset 100% Fuel Level Electrical ConfigFactory Defaults Firmware UpdatesPage Network management interfaces ATS Management OptionsOverview InfraStruXure ManagerConnect the ATS to the InfraStruXure Manager Configuring the InfraStruXure ManagerConnect the ATS to your network Configuring the ATS Network Management InterfaceTCP/IP configuration methods Configuration overviewDevice IP Configuration Wizard Bootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Remote access to the control console Local access to the control consoleChoose Network from the Control Console menu Control consoleWeb interface How to Access the ATS Network Management InterfaceSnmp Telnet and SSHFTP and SCP InfraStruXure Power Generation System Customizing and Updating the ATS How to connect contacts to the user interface board EPO Test NC no How to Connect an EPO Switch to the ATSContact Closure-Normally Open Problem Action Safety warnings How to Allow Easy Access to the ATS Display Interface Part Number Description Height on Panel Output distribution circuit breakers available from APCCircuit breaker adapter modules available from APC Determine the configuration of the panelCombination #1 Allowed circuit breaker combinationsCombination #6 T1 three-pole breaker requires no additional preparation Preparing the breakers for installationT1 three-pole breaker assembly Parts and tools needed for installation proceduresInstalling breakers on the ATS panel bus See also From a local computer How to Download Firmware UpdatesPhysical ElectricalAWG Installation and Wiring 208V 480VCompliance EnvironmentalPage If Source 2 is a Second Utility Appendix Custom InstallationsInfraStruXure Power Generation System Index InfraStruXure Power Generation System InfraStruXure Power Generation System Page Page Page Radio Frequency Interference 990-1845C