Appendix: Custom Installations

If Source 2 is a Second Utility

Differences in your system from information presented in this manual

The ATS was designed for operation with an APC InfraStruXure generator, and this manual assumes that Source 2 is an APC InfraStruXure generator. If using a secondary utility instead of a generator, almost all references to the “generator” should be considered references to your second utility as well. However, the following sections will not apply to your system and should be disregarded:

“Generator start sequence” on page 7

“Generator cool-down” on page 7

“Fuel monitoring/runtime calculation” on page 9

“Communication converter,” (item 4) on page 13

“Resetting automatic operation on the generator” on page 20

“Generator” on page 37

“Fuel Alarm Limits” on page 44

If your installation includes a secondary utility source, the APC Field Service Engineer performing your start-up will configure your ATS to operate with two utility sources.

Note

InfraStruXure Power Generation System

81

Image 91
Contents Operation Page Companion manuals How to find updates to this manualAbout This Manual AudiencePage Contents Display Interface Communication Configuration Customizing and Updating the ATS Specifications Page Cross-reference symbols used in this manual Safety symbols used in this manualOverview Wire sizing Total power off procedure InstallationOperating environment Page Overview InfraStruXure Power Generation SystemSystem Operates How the InfraStruXure Power GenerationGenerator cool-down Generator start sequenceOpen and closed transfers Fuel monitoring/runtime calculation Page Front view, door closed Smart Distribution Panel with ATS The automatic operation Control panel is used to set Front view, door openATS panel board, left side Installation Manual for instructionsATS panel board, right side ATS Component Details Motorized switchesUser connection plate Automatic operation control panelATS monitoring unit  When the EPO Arm/Test rocker is in the TestATS label kit Automatic Operation OperationAutomatic Operation Problem-loss of automatic operation Emergency Manual Operation Set the ATS Automatic Operation switch to Disable How to power the load from the generatorEmergency Manual Operation How to return to powering the load from utility Press Total Power Off Total Power Off Display Interface Top-level menu screen Top-level status screensNavigating through screens Password-protected screensTotal Load Summary Total Load by PhasePower Factor Load-MeterATS Position ATS/VoltageS1-Utility S2-Generator ATS Setup ATS/Voltage Generator Status GeneratorGen Output Adjust Operating SettingsManufacturer Data View Test Log TestingRun/View Test Test Duration Test ScheduleHow a test occurs Reset All ResetStats Alarm Setup AlarmsView Active Alarms Alarm/Event LogOther Limits Alarm BeeperClearing latched alarms Fuel Alarm LimitsDate/Time ConfigSystem Password System/NetworkPage Reset 100% Fuel Level Electrical ConfigFactory Defaults Firmware UpdatesPage Network management interfaces ATS Management OptionsOverview InfraStruXure ManagerConnect the ATS to the InfraStruXure Manager Configuring the InfraStruXure ManagerConnect the ATS to your network Configuring the ATS Network Management InterfaceTCP/IP configuration methods Configuration overviewDevice IP Configuration Wizard Bootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Remote access to the control console Local access to the control consoleChoose Network from the Control Console menu Control consoleWeb interface How to Access the ATS Network Management InterfaceSnmp Telnet and SSHFTP and SCP InfraStruXure Power Generation System Customizing and Updating the ATS How to connect contacts to the user interface board EPO Test NC no How to Connect an EPO Switch to the ATSContact Closure-Normally Open Problem Action Safety warnings How to Allow Easy Access to the ATS Display Interface Part Number Description Height on Panel Output distribution circuit breakers available from APCCircuit breaker adapter modules available from APC Determine the configuration of the panelCombination #1 Allowed circuit breaker combinationsCombination #6 T1 three-pole breaker requires no additional preparation Preparing the breakers for installationT1 three-pole breaker assembly Parts and tools needed for installation proceduresInstalling breakers on the ATS panel bus See also From a local computer How to Download Firmware UpdatesPhysical ElectricalAWG Installation and Wiring 208V 480VCompliance EnvironmentalPage If Source 2 is a Second Utility Appendix Custom InstallationsInfraStruXure Power Generation System Index InfraStruXure Power Generation System InfraStruXure Power Generation System Page Page Page Radio Frequency Interference 990-1845C