American Power Conversion 250 A ATS panel board, left side, Installation Manual for instructions

Page 23

Smart Distribution Panel with ATS

ATS panel board, left side

 

The handle aids removal of the panel board

assembly from the ATS enclosure. At least

two people are required to remove the panel

board assembly (refer to the Electrical

 

Installation Manual for instructions).

 

 

The Source 1 fuse block regulates input to

 

the Source 1 control transformer for

subsequent powering of the Source 1

 

motorized switch and ATS monitoring unit.

The Source 1 control transformer outputs

 

 

120 VAC and 18 VAC to the Source 1

 

motorized switch and the ATS monitoring

 

unit after stepping down the 480 V or 208 V

 

input.

 

The communication converter allows the

 

generator and the ATS to communicate.

The ATS monitoring unit houses a central

 

board assembly that communicates with

 

several monitoring boards located

throughout the ATS (see “ATS monitoring

unit” on page 17 for detailed information).

 

 

Behind this access panel is the ATS interface

 

circuit board. Use a Phillips or standard

 

screwdriver to remove the panel.

The Source 2 input switch accepts input

wires from the generator (refer to the

 

 

Electrical Installation Manual for

 

connection instructions).

 

WARNING: Only a certified electrician

 

should connect the generator to the ATS!

This switch and fuse block regulate the 120 VAC supply to the generator for powering the block heater and battery charger.

The wheel extensions on the panel board assembly allow removal of the assembly during installation. Removing the panel board assembly makes it easier to pull wires into the ATS.

InfraStruXure Power Generation System

13

Image 23
Contents Operation Page Companion manuals How to find updates to this manualAbout This Manual AudiencePage Contents Display Interface Communication Configuration Customizing and Updating the ATS Specifications Page Overview Safety symbols used in this manualCross-reference symbols used in this manual Wire sizing Operating environment InstallationTotal power off procedure Page Overview InfraStruXure Power Generation SystemSystem Operates How the InfraStruXure Power GenerationGenerator cool-down Generator start sequenceOpen and closed transfers Fuel monitoring/runtime calculation Page Front view, door closed Smart Distribution Panel with ATS The automatic operation Control panel is used to set Front view, door openATS panel board, left side Installation Manual for instructionsATS panel board, right side ATS Component Details Motorized switchesUser connection plate Automatic operation control panelATS monitoring unit  When the EPO Arm/Test rocker is in the TestATS label kit Automatic Operation OperationAutomatic Operation Problem-loss of automatic operation Emergency Manual Operation Set the ATS Automatic Operation switch to Disable How to power the load from the generatorEmergency Manual Operation How to return to powering the load from utility Press Total Power Off Total Power Off Display Interface Top-level menu screen Top-level status screensNavigating through screens Password-protected screensTotal Load Summary Total Load by PhasePower Factor Load-MeterS1-Utility ATS/VoltageATS Position S2-Generator ATS Setup ATS/Voltage Generator Status GeneratorManufacturer Data Operating SettingsGen Output Adjust Run/View Test TestingView Test Log Test Duration Test ScheduleHow a test occurs Stats ResetReset All Alarm Setup AlarmsView Active Alarms Alarm/Event LogOther Limits Alarm BeeperClearing latched alarms Fuel Alarm LimitsDate/Time ConfigSystem Password System/NetworkPage Reset 100% Fuel Level Electrical ConfigFactory Defaults Firmware UpdatesPage Network management interfaces ATS Management OptionsOverview InfraStruXure ManagerConnect the ATS to the InfraStruXure Manager Configuring the InfraStruXure ManagerConnect the ATS to your network Configuring the ATS Network Management InterfaceDevice IP Configuration Wizard Configuration overviewTCP/IP configuration methods Bootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Remote access to the control console Local access to the control consoleChoose Network from the Control Console menu Control consoleWeb interface How to Access the ATS Network Management InterfaceSnmp Telnet and SSHFTP and SCP InfraStruXure Power Generation System Customizing and Updating the ATS How to connect contacts to the user interface board EPO Test NC no How to Connect an EPO Switch to the ATSContact Closure-Normally Open Problem Action Safety warnings How to Allow Easy Access to the ATS Display Interface Part Number Description Height on Panel Output distribution circuit breakers available from APCCircuit breaker adapter modules available from APC Determine the configuration of the panelCombination #1 Allowed circuit breaker combinationsCombination #6 T1 three-pole breaker requires no additional preparation Preparing the breakers for installationT1 three-pole breaker assembly Parts and tools needed for installation proceduresInstalling breakers on the ATS panel bus See also From a local computer How to Download Firmware UpdatesPhysical ElectricalAWG Installation and Wiring 208V 480VCompliance EnvironmentalPage If Source 2 is a Second Utility Appendix Custom InstallationsInfraStruXure Power Generation System Index InfraStruXure Power Generation System InfraStruXure Power Generation System Page Page Page Radio Frequency Interference 990-1845C