American Power Conversion 250 A manual Generator Status

Page 47

Generator

Generator Status

Fuel & Runtime

Statistics & Maint.

Generator Settings

Generator Status

The following items are available on this menu:

Generator Status This screen displays the following conditions to describe the Gen State:

Off: The generator is not running.

Cranking: The generator is starting.

Running: The generator is running.

Idle: The generator is running, but not supplying power to the load.

E-Stop: The Emergency Power-Off switch has been actuated on the generator or the ATS.

Fault: The generator is unable to start.

No Com: The ATS has lost communication with the generator.

Mode Sw provides the position of the generator’s /Manual/Auto switch. The switch must be in Auto for the generator to start, based on the state of the run/stop contact. Auto, Manual, or Off is displayed to describe the position of the switch.

The following settings can be accessed through this menu:

Engine Run: Shows the current state of the run/stop contact, which signals the generator's engine to start and stop. The state can be Run or Off. Automatic control of this signal is disabled when the Not in Automatic Operation LED on the ATS is lit.

Engine Parameters: View the following measured data relating to operation of the generator's engine:

–Battery Voltage

–Engine RPM

–Oil Pressure

–Coolant Level

–Coolant Temperature

–Oil Level

Fuel & Runtime This screen displays the following:

Type: The type of fuel the generator uses (diesel).

Tank Size: The size of the fuel tank on the generator (in gallons or liters).

Fuel Level: The percentage of fuel left in the generator fuel tank.

Runtime Estimate: How much time (xx days zz hours) the generator can run based on the fuel level and load, and the load value (in kW) used to calculate runtime.

Statistics & Maint. Lifetime Statistics: Scroll through a list of items that accumulates over the life of the generator, including:

Last Maintenance Date

Engine Starts

Total kWh

Total Runhours

InfraStruXure Power Generation System

37

Image 47
Contents Operation Page Companion manuals How to find updates to this manualAbout This Manual AudiencePage Contents Display Interface Communication Configuration Customizing and Updating the ATS Specifications Page Overview Safety symbols used in this manualCross-reference symbols used in this manual Wire sizing Operating environment InstallationTotal power off procedure Page Overview InfraStruXure Power Generation SystemSystem Operates How the InfraStruXure Power GenerationGenerator cool-down Generator start sequenceOpen and closed transfers Fuel monitoring/runtime calculation Page Front view, door closed Smart Distribution Panel with ATS The automatic operation Control panel is used to set Front view, door openATS panel board, left side Installation Manual for instructionsATS panel board, right side ATS Component Details Motorized switchesUser connection plate Automatic operation control panelATS monitoring unit  When the EPO Arm/Test rocker is in the TestATS label kit Automatic Operation OperationAutomatic Operation Problem-loss of automatic operation Emergency Manual Operation Set the ATS Automatic Operation switch to Disable How to power the load from the generatorEmergency Manual Operation How to return to powering the load from utility Press Total Power Off Total Power Off Display Interface Top-level menu screen Top-level status screensNavigating through screens Password-protected screensTotal Load Summary Total Load by PhasePower Factor Load-MeterS1-Utility ATS/VoltageATS Position S2-Generator ATS Setup ATS/Voltage Generator Status GeneratorManufacturer Data Operating SettingsGen Output Adjust Run/View Test TestingView Test Log Test Duration Test ScheduleHow a test occurs Stats ResetReset All Alarm Setup AlarmsView Active Alarms Alarm/Event LogOther Limits Alarm BeeperClearing latched alarms Fuel Alarm LimitsDate/Time ConfigSystem Password System/NetworkPage Reset 100% Fuel Level Electrical ConfigFactory Defaults Firmware UpdatesPage Network management interfaces ATS Management OptionsOverview InfraStruXure ManagerConnect the ATS to the InfraStruXure Manager Configuring the InfraStruXure ManagerConnect the ATS to your network Configuring the ATS Network Management InterfaceDevice IP Configuration Wizard Configuration overviewTCP/IP configuration methods Bootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Remote access to the control console Local access to the control consoleChoose Network from the Control Console menu Control consoleWeb interface How to Access the ATS Network Management InterfaceSnmp Telnet and SSHFTP and SCP InfraStruXure Power Generation System Customizing and Updating the ATS How to connect contacts to the user interface board EPO Test NC no How to Connect an EPO Switch to the ATSContact Closure-Normally Open Problem Action Safety warnings How to Allow Easy Access to the ATS Display Interface Part Number Description Height on Panel Output distribution circuit breakers available from APCCircuit breaker adapter modules available from APC Determine the configuration of the panelCombination #1 Allowed circuit breaker combinationsCombination #6 T1 three-pole breaker requires no additional preparation Preparing the breakers for installationT1 three-pole breaker assembly Parts and tools needed for installation proceduresInstalling breakers on the ATS panel bus See also From a local computer How to Download Firmware UpdatesPhysical ElectricalAWG Installation and Wiring 208V 480VCompliance EnvironmentalPage If Source 2 is a Second Utility Appendix Custom InstallationsInfraStruXure Power Generation System Index InfraStruXure Power Generation System InfraStruXure Power Generation System Page Page Page Radio Frequency Interference 990-1845C