Spindle Break-In
NOTICE
Successfully complete all of the spindle
To
1.Successfully complete the Test Run proce- dure beginning on Page 16.
2.DISCONNECT LATHE FROM POWER!
3.Make sure the carriage is disengaged from the leadscrew and feed rod (refer to Step 6 on Page 17 for instructions).
4.Set the lathe to a spindle speed of 60 RPM (refer to Setting Spindle Speed on Page 38 for detailed instructions).
5.Connect the machine to power and move the spindle lever down to start the spindle rotat- ing counterclockwise, then let the lathe run for 20 minutes.
6.Move the spindle lever to the center position, wait for the spindle to come to a complete stop, then move the spindle lever up to start the spindle rotating in the opposite direction (clockwise). Let the lathe run for another 20 minutes.
7.Repeat Steps
Model G0554Z (Mfg 01/09+)
8.Turn the lathe OFF and allow the spindle to come to a complete stop, then disconnect the lathe from power.
9.Place your hand on the spindle to test its operational temperature.
Recommended
Adjustments
For your convenience, the adjustments listed below have been performed at the factory.
However, because of the many variables involved with shipping, we recommend that you at least verify the following adjustments to ensure the best possible results from your new machine.
Factory adjustments that should be verified:
•Tailstock alignment (Page 33).
•Cross slide backlash adjustment (Page 58).
•Gib adjustments (Page 58).
NOTICE
After the first 16 hours of use, the