8.7.7 Set-up of block (Step 6)

It is possible to set the block for each group as an operation block. This operation block can be also used for the charge calculation.

Set the block groups. [Procedure]

1)Select a floor using the “/ ” button

From the Block Settings window, use the “ /” button to select the floor.

2)Click the group icon.

Select the Group icon to be added to a block by clicking on it. More than one group may be selected at one time. Click on a selected group to deselect it .

(The selected icon is displayed with red frame.)

3)Click [Block Set ] button.

With the Group icon selected, click on the [Block Set] button. A Block Settings and Naming window appears.

4)Select either New or Exist.

In the Block Settings and Naming window, use the option buttons to select either a new block name setting or an existing block.

5)Enter a block name or select a block name. To enter a new block name, just enter the name. To work with an existing block, select the block name.

6)Click [OK] button.

Click the [OK] button after setting the block name. The label “Block**” appears in the group icon. (**: Block No.)

7)Repeat steps 1) to 6).

Set the blocks for the groups on each floor.

8)Click [OK] button.

When finished setting blocks, click the [OK] button.

*When the [Cancel] button is clicked, this setting is terminated to return to the initial window.

Name Change button

Block Set button

Release button

Set-up of block screen

Group icon select/non-select state

Block Settings and Naming window

Note:

Block names may contain a maximum of 20 characters.

Up to 2000 blocks can be set.

If all group icons are not assigned to a block, a warning message appears. Correct this error to proceed.

When using the charge function, groups not assigned to blocks will not show up in the charge information. Be sure to assign all groups to a block.

This block is not concerned with G-50A browser block setting, but is a setting of independent block.

Deleting block settings

Follow these steps to delete block settings for a group. [Procedure]

1)Click the group icon.

Select the group icon whose block settings you wish to delete by clicking on its icon.

2)Click [Release] button.

Select the [Release] button and the block settings for the selected group are erased. The “Block**” label in the group icon disappears.

Note:

If a named block has no groups assigned to it, a message appears asking if it is okay to delete the block itself. To delete the block itself, click the [OK] button; to keep the block, click the [Cancel] button.

38

Image 41
Contents Please keep this manual for future use Please read this manual before using the unitContents Page Do not use with other applications Safety PrecautionsOther machines ¡ *1 System Requirements Requirements system recommendationsCompatible Units Restrictions RestrictionsNumber of units M e Manufacturer Model Other DevicesHardware Connection Diagram System Configuration System Configuration ExampleTools for Site Adjustment Flow of Site AdjustmentPC connections and settings 50A test runD e l s IP address range Test operation from centralized controller G-50APage G-2000A Setup InstallationPreparing for installation Steps Action Details How toMsde setup Running TG-2000A Setup New setupDatabase setup When the installation is completed, restart the computerInstallation start confirmation Check the installation folderTG-2000A setup completion Read the license agreementMsde uninstall G-2000A UninstallTG-2000A uninstall Part Names and Functions Window Elements Basic Mouse Operation Accessing Functions and Moving between WindowsShift from the initial window to the control window Shift from the control window to the initial windowPage Page User Set -up Set TG -2000A functions Page Page Startup Initial Startup and Shutdown Before StartupShutting down the OS ShutdownTG-2000A Shutdown System Setting Procedure System Setting Procedure System Setting ScreenGeneral Operation User Set-upReliability Function Connection SettingSite Name Set-up Energy Monitoring RelatedPage G-50 Connection Set-up Setting Procedure and RestrictionsNumber of G-50A se t-up Step IP address of G-50A se t-up StepMonitor the optional functions being used. Procedure System Configuration Set-upUnit composition set-up Step 2 G-50A data collection StepIcon Name Address range Change the unit configuration. ProcedureSe t-up of refrigerant system Step Set-up of group Step Change the group No. Procedure Interlocked setting StepInterlocking ventilation unit Interlocking destination un-set unitSet-up of model name Step Configuration Procedure and RestrictionsMonitoring Screen Set-up Set-up of the number of floors, and floor name Step Set-up of floor name and G -50 Creation of a plane view StepFloor Selection Display Button Set-up of icon arrange and name StepSet the group icons on each floor and set their names Group ListDeleting block settings Set the block groups. ProcedureSet-up of block Step Name Change button Block Set button Release buttonChanging the block name Check before WHM setup. Procedure Setting Procedures and RestrictionsModel Baud rate Parity Stop bit Energy Monitoring S e t-up Set Charge System options. ProcedureDivision mode for outdoor unit Division mode StepDivision mode for indoor unit Proportiona l division reference dataDelete Watt Hour Meter Relationships Select the OC icon, and click on the selected outdoor unitDeleting Watt Hour Meter Relationships Relation between indoor units and watt hour meters StepSet the Indoor Unit and Watt Hour Meter Relationship Charge Blocks Step Set the charge blocks. ProcedureAdd charge blocks Delete the charge blockRelease a block from charge blocks Manually Setting the Currency Selecting a Currency from the Display ProcedureExit the Currency Settings Set the electric power rate schedule. Procedure10Standard charge set Step Set the standard charge . ProcedureTime Set-up Function ContentsSet the date/time . Procedure Monitor button Monitor the timeChange the password Password S e t-upNo repair is required Overview Remarks Preparing for Charging Data Maintenance Maintenance of Charge DataMaintenance Methods and Restrictions Display the Maintenance screen. ProcedureMaintaining Apportioned Unit Data Unit Data MaintenanceCorrection method Maintenance example Maintaining watt hour Meter Data Procedure Watt Hour Meter Data MaintenanceDescription of function Watt hour Meter Monitor Function ProcedureOperation Amount Data Monitoring Monitor the data for the last day after Charge Parameter OutputMonitoring operation amount data Performing charging remedy Charging RemedyOutput file data format Preparation Preparing to perform charging remedyApportioning integrated Remark InterVal Remedial apportioning setting screenRemedial apportioning confirmation screen Calculating screen Remedy when personal computer HDD fails no backup Remedy when personal computer HDD fails backup Day before recovery day Apportioning method when computer crashes Remedy when watt hour meter fails monitoring impossible Integrate d Remedy for system information setting error Total air-conditioning charge including that Air-conditioning unit error codes Error Code ListPage Page System error codes Detail of function Setting Check ListSetting item Case Test run check sheet Test Run CheckLRC Date Tester Test item Comment Charging Test Run CheckCharging No WHM connection Test Run Check Page Capacity Setting Division mode Charge settingCheck Within Outside TotalExample 1100 conditioner 1300 Outside Within 12001400 Page Page WHM1 WHM2 WHM3 WHM4 WHM5 WHM6 Memo Setup Procedure Appendix 1 Installing Windows XP ProfessionalPreparing for Se tup What you needPage Windows Appendix 2 Auto Log-in Confirmation MethodWindows XP Page WT03901X01