4.3Step 1: Test operation from centralized controller G-50A

Perform only the test operation of the air-conditioning system of the central controller G-50A.

(1)Preliminary check

Check that the test operation of the air conditioner has been completed. Check that the central controller G-50A is set to Group and Interlock.

(The initial setting is executable using the initial setting tool or the G-50A.)

HUB

Integrated centralized

control software

TG-2000A

Power supply unit

G-50A

Step 1

(2)Test operation from central controller G-50A

After supplying power to the central controller G-50A and all air conditioners, perform the test operation from the central controller G-50A, and check the operation state of each unit.

*For the test operation method, refer to the installation manual for the air conditioner or the central controller G-50A.

4.4Step 2: Initial setting of integrated centralized control software TG-2000A

(1)Set -up of integrated centralized control software TG -2000A

Make preparations to allow the personal computer to be operative in order to install the integrated centralized control software TG -2000A. After performing the set-up preparations, set up the integrated centralized control software TG -2000A.

Note:

For the set -up procedure, refer to Chapter 5.

For safety, check the installation state/connection before turning the power ON.

(2)Check the G-50A IP address and personal computer (which uses the integrated centralized control software)

Check the G-50A IP address. Check the IP address used for the integrated centralized control software at the same time. Normally, set the sub-net to "255.255.255.0".

For a LAN dedicated to the G-50A system, it is recommended to set the IP address within the following range.

M o d e l s

IP address range

G-50A main unit

[ 1 9 2 . 1 6 8 . 1 . 1 ] to [192 . 168 . 1 . 40]

Personal computer for browser

[192.168.1.101]to [192 . 168 . 1 . 149]

Personal computer

[192 . 168 .1 . 150]

for integrated centralzed control software

 

 

 

PLC

[192.168.1.151]to [192 . 168 . 1 . 200]

Personal computer of initial setting tool

[192 . 168 . 1 . 201]

*To connect to the existing LAN, set the IP address and sub-net mask set by the LAN manager.

(3)LAN connection confirmation

Check that the LAN cable is connected to the G-50A, personal computer (using integrated software), and hub, and that power is supplied to the hub.

(4)Initial setting of integrated centralized control software

Start the integrated centralized control software TG -2000A to execute the initial setting.

Note:

For the initial setting method of the integrated software, refer to Chapters 6 to 8.

7

Image 10
Contents Please read this manual before using the unit Please keep this manual for future useContents Page Other machines Safety PrecautionsDo not use with other applications Compatible Units System Requirements Requirements system recommendations¡ *1 Number of units RestrictionsRestrictions Other Devices M e Manufacturer ModelSystem Configuration System Configuration Example Hardware Connection DiagramPC connections and settings Flow of Site AdjustmentTools for Site Adjustment 50A test runTest operation from centralized controller G-50A D e l s IP address rangePage Preparing for installation InstallationG-2000A Setup Steps Action Details How toDatabase setup Running TG-2000A Setup New setupMsde setup When the installation is completed, restart the computerTG-2000A setup completion Check the installation folderInstallation start confirmation Read the license agreementTG-2000A uninstall G-2000A UninstallMsde uninstall Part Names and Functions Window Elements Shift from the initial window to the control window Accessing Functions and Moving between WindowsBasic Mouse Operation Shift from the control window to the initial windowPage Page User Set -up Set TG -2000A functions Page Page Initial Startup and Shutdown Before Startup StartupTG-2000A Shutdown ShutdownShutting down the OS System Setting Procedure System Setting Screen System Setting ProcedureUser Set-up General OperationConnection Setting Reliability FunctionEnergy Monitoring Related Site Name Set-upPage Number of G-50A se t-up Step Setting Procedure and RestrictionsG-50 Connection Set-up IP address of G-50A se t-up StepSystem Configuration Set-up Monitor the optional functions being used. Procedure2 G-50A data collection Step Unit composition set-up StepChange the unit configuration. Procedure Icon Name Address rangeSe t-up of refrigerant system Step Set-up of group Step Interlocking ventilation unit Interlocked setting StepChange the group No. Procedure Interlocking destination un-set unitMonitoring Screen Set-up Configuration Procedure and RestrictionsSet-up of model name Step Set-up of the number of floors, and floor name Step Creation of a plane view Step Set-up of floor name and G -50Set the group icons on each floor and set their names Set-up of icon arrange and name StepFloor Selection Display Button Group ListSet-up of block Step Set the block groups. ProcedureDeleting block settings Name Change button Block Set button Release buttonChanging the block name Setting Procedures and Restrictions Check before WHM setup. ProcedureModel Baud rate Parity Stop bit Set Charge System options. Procedure Energy Monitoring S e t-upDivision mode for indoor unit Division mode StepDivision mode for outdoor unit Proportiona l division reference dataSelect the OC icon, and click on the selected outdoor unit Delete Watt Hour Meter RelationshipsSet the Indoor Unit and Watt Hour Meter Relationship Relation between indoor units and watt hour meters StepDeleting Watt Hour Meter Relationships Set the charge blocks. Procedure Charge Blocks StepRelease a block from charge blocks Delete the charge blockAdd charge blocks Exit the Currency Settings Selecting a Currency from the Display ProcedureManually Setting the Currency Set the electric power rate schedule. ProcedureSet the standard charge . Procedure 10Standard charge set StepSet the date/time . Procedure Function ContentsTime Set-up Monitor the time Monitor buttonPassword S e t-up Change the passwordNo repair is required Overview Remarks Maintenance Methods and Restrictions Maintenance of Charge DataPreparing for Charging Data Maintenance Display the Maintenance screen. ProcedureUnit Data Maintenance Maintaining Apportioned Unit DataCorrection method Maintenance example Watt Hour Meter Data Maintenance Maintaining watt hour Meter Data ProcedureOperation Amount Data Monitoring Watt hour Meter Monitor Function ProcedureDescription of function Monitoring operation amount data Charge Parameter OutputMonitor the data for the last day after Output file data format Charging RemedyPerforming charging remedy Preparing to perform charging remedy PreparationRemedial apportioning setting screen Apportioning integrated Remark InterValRemedial apportioning confirmation screen Calculating screen Remedy when personal computer HDD fails no backup Remedy when personal computer HDD fails backup Day before recovery day Apportioning method when computer crashes Remedy when watt hour meter fails monitoring impossible Integrate d Remedy for system information setting error Total air-conditioning charge including that Error Code List Air-conditioning unit error codesPage Page System error codes Setting item Case Setting Check ListDetail of function Test Run Check Test run check sheetLRC Date Tester Charging No WHM connection Test Run Check Charging Test Run CheckTest item Comment Page Capacity Check Within Outside Division mode Charge settingSetting TotalExample 1100 conditioner 1300 Outside Within 12001400 Page Page WHM1 WHM2 WHM3 WHM4 WHM5 WHM6 Memo Preparing for Se tup Appendix 1 Installing Windows XP ProfessionalSetup Procedure What you needPage Windows XP Appendix 2 Auto Log-in Confirmation MethodWindows Page WT03901X01