Mitsubishi Electronics TG-2000A operation manual Monitor the time, Monitor button

Page 54

Note:

Don’t change time in the following cases. However, this only applies when the charge function is on. Because charge collection processing is performed.

When the current time is between 04:00 and 07:00.

We recommend that the time be checked and corrected once a month.

Execute the correction of time within time of 08:00 to 21:45.When the RS -485 WHM is used, however, do not correct the time near the charge zone change time.

The date display order depends on the OS setting.

When the date is exceeded after the start of operation and the time is reset, air-conditioning charge calculation may not be performed correctly.

Maintenance Tip

Set these time and date settings from the TG-2000A application. When the TG-2000A program is running, do not change the Windows system time. Changing the Windows clock will not change the TG -2000A clock.

Don't change the date(and the time over the day), When charge function is used.Otherwise,the charge calculation may not be executed properly.

Monitor the time.

Monitor the year/month/day of the PC and connected G-50A . [Procedure]

1)Select [Time set -up] button.

Click the [Time set-up] button located in the system setting group on the initial window.

2)Select [Time monitor].

Click the [Time monitor] button on the time set-up select screen.

3)Select the [Monitor] button.

In this case, click the [Monitor] button on the time monitor screen. When the button is clicked, the differ- ence between the date/time of all G-50A units connected to the PC (personal computer) on which the integrated centralized control software TG -2000A operates and the reference machine is displayed.

* There is a difference of several seconds depending

Time monitor window

on the monitor timing.

 

4)Select [OK] button.

When the time confirmation is completed, click the [OK] button, and the initial screen returns.

 

Monitor button

Display of PC date/time

Difference from

reference machine

 

 

(G-50A No.1)

Display of G-50A

 

date/time

 

New time monitor window

51

Image 54
Contents Please read this manual before using the unit Please keep this manual for future useContents Page Safety Precautions Other machinesDo not use with other applications System Requirements Requirements system recommendations Compatible Units¡ *1 Restrictions Number of unitsRestrictions Other Devices M e Manufacturer ModelSystem Configuration System Configuration Example Hardware Connection DiagramPC connections and settings Flow of Site AdjustmentTools for Site Adjustment 50A test runTest operation from centralized controller G-50A D e l s IP address rangePage Preparing for installation InstallationG-2000A Setup Steps Action Details How toDatabase setup Running TG-2000A Setup New setupMsde setup When the installation is completed, restart the computerTG-2000A setup completion Check the installation folderInstallation start confirmation Read the license agreementG-2000A Uninstall TG-2000A uninstallMsde uninstall Part Names and Functions Window Elements Shift from the initial window to the control window Accessing Functions and Moving between WindowsBasic Mouse Operation Shift from the control window to the initial windowPage Page User Set -up Set TG -2000A functions Page Page Initial Startup and Shutdown Before Startup StartupShutdown TG-2000A ShutdownShutting down the OS System Setting Procedure System Setting Screen System Setting ProcedureUser Set-up General OperationConnection Setting Reliability FunctionEnergy Monitoring Related Site Name Set-upPage Number of G-50A se t-up Step Setting Procedure and RestrictionsG-50 Connection Set-up IP address of G-50A se t-up StepSystem Configuration Set-up Monitor the optional functions being used. Procedure2 G-50A data collection Step Unit composition set-up StepChange the unit configuration. Procedure Icon Name Address rangeSe t-up of refrigerant system Step Set-up of group Step Interlocking ventilation unit Interlocked setting StepChange the group No. Procedure Interlocking destination un-set unitConfiguration Procedure and Restrictions Monitoring Screen Set-upSet-up of model name Step Set-up of the number of floors, and floor name Step Creation of a plane view Step Set-up of floor name and G -50Set the group icons on each floor and set their names Set-up of icon arrange and name StepFloor Selection Display Button Group ListSet-up of block Step Set the block groups. ProcedureDeleting block settings Name Change button Block Set button Release buttonChanging the block name Setting Procedures and Restrictions Check before WHM setup. ProcedureModel Baud rate Parity Stop bit Set Charge System options. Procedure Energy Monitoring S e t-upDivision mode for indoor unit Division mode StepDivision mode for outdoor unit Proportiona l division reference dataSelect the OC icon, and click on the selected outdoor unit Delete Watt Hour Meter RelationshipsRelation between indoor units and watt hour meters Step Set the Indoor Unit and Watt Hour Meter RelationshipDeleting Watt Hour Meter Relationships Set the charge blocks. Procedure Charge Blocks StepDelete the charge block Release a block from charge blocksAdd charge blocks Exit the Currency Settings Selecting a Currency from the Display ProcedureManually Setting the Currency Set the electric power rate schedule. ProcedureSet the standard charge . Procedure 10Standard charge set StepFunction Contents Set the date/time . ProcedureTime Set-up Monitor the time Monitor buttonPassword S e t-up Change the passwordNo repair is required Overview Remarks Maintenance Methods and Restrictions Maintenance of Charge DataPreparing for Charging Data Maintenance Display the Maintenance screen. ProcedureUnit Data Maintenance Maintaining Apportioned Unit DataCorrection method Maintenance example Watt Hour Meter Data Maintenance Maintaining watt hour Meter Data ProcedureWatt hour Meter Monitor Function Procedure Operation Amount Data MonitoringDescription of function Charge Parameter Output Monitoring operation amount dataMonitor the data for the last day after Charging Remedy Output file data formatPerforming charging remedy Preparing to perform charging remedy PreparationRemedial apportioning setting screen Apportioning integrated Remark InterValRemedial apportioning confirmation screen Calculating screen Remedy when personal computer HDD fails no backup Remedy when personal computer HDD fails backup Day before recovery day Apportioning method when computer crashes Remedy when watt hour meter fails monitoring impossible Integrate d Remedy for system information setting error Total air-conditioning charge including that Error Code List Air-conditioning unit error codesPage Page System error codes Setting Check List Setting item CaseDetail of function Test Run Check Test run check sheetLRC Date Tester Charging Test Run Check Charging No WHM connection Test Run CheckTest item Comment Page Capacity Check Within Outside Division mode Charge settingSetting TotalExample 1100 conditioner 1300 Outside Within 12001400 Page Page WHM1 WHM2 WHM3 WHM4 WHM5 WHM6 Memo Preparing for Se tup Appendix 1 Installing Windows XP ProfessionalSetup Procedure What you needPage Appendix 2 Auto Log-in Confirmation Method Windows XPWindows Page WT03901X01