Mitsubishi Electronics TG-2000A operation manual Test Run Check, Test run check sheet

Page 82

11.2 Test Run Check

Note:

Before carrying out a test run check, complete the test run checks of the systems under the control of the central controller G-50A .

See Chapter 3 for details on site adjustment.

Test run check sheet

Once the initial settings have been carried out as prescribed by the section on field adjustment in this manual, follow the order of testing prescribed by the test run check sheet and check the following items: (1) t o (4).

(1)Check operation start -up.

Once the necessary information has been entered in the initial screen, advance to the control screen.

Check that the screen which indicates operation start -up is in progress appears.

The time depends on the number of air conditioners that are connected. The operation start-up should take between 10 to 20 minutes to complete.

Check the display of each floor to make sure there is no error mark.

If an error occurs, check the error history on the history screen.

(2)Man-machine on-off (on-off from the integrated centralized control software TG-2000A)

Operate an air conditioner unit from the man-machine.

Confirm the displays of the local remote controller, central controller G-50A, system controller and man-machine indicate the air conditioner is operating.

Carry out air conditioner operation in order of group, block, floor and entire building.

If operation from the man-machine operated the wrong air conditioner, check the following settings.

àPosition and name of group icon setting (S ee section 8. 7 . 6)

àIndoor unit and ventilation group setting (See section 8. 6 . 5)

àBlock setting (See section 8. 7 . 7)

(3)Local remote controller on-off

* This step is only required when a local remote controller is connected.

Operate the air conditioner unit from the local remote controller.

Confirm the central controller G-50A and man-machine indicates that the air conditioner unit is operating.

On the man-machine display, check the floor screen, block screen and entire building screen are correct.

(4)Central controller G-50A on-off

Operate the air conditioner unit from the central controller G-50A .

Confirm the local remote controller and man-machine indicates that the air conditioner unit is operating.

On the man-machine display, check the fl oor screen, block screen and entire building screen are correct.

To make the check sheets easy to read, allocate 1 check sheet page for each installation floor unit or central controller G-50A unit.

79

Image 82
Contents Please read this manual before using the unit Please keep this manual for future useContents Page Other machines Safety PrecautionsDo not use with other applications Compatible Units System Requirements Requirements system recommendations¡ *1 Number of units RestrictionsRestrictions Other Devices M e Manufacturer ModelSystem Configuration System Configuration Example Hardware Connection DiagramPC connections and settings Flow of Site AdjustmentTools for Site Adjustment 50A test runTest operation from centralized controller G-50A D e l s IP address rangePage Preparing for installation InstallationG-2000A Setup Steps Action Details How toDatabase setup Running TG-2000A Setup New setupMsde setup When the installation is completed, restart the computerTG-2000A setup completion Check the installation folderInstallation start confirmation Read the license agreementTG-2000A uninstall G-2000A UninstallMsde uninstall Part Names and Functions Window Elements Shift from the initial window to the control window Accessing Functions and Moving between WindowsBasic Mouse Operation Shift from the control window to the initial windowPage Page User Set -up Set TG -2000A functions Page Page Initial Startup and Shutdown Before Startup StartupTG-2000A Shutdown ShutdownShutting down the OS System Setting Procedure System Setting Screen System Setting ProcedureUser Set-up General OperationConnection Setting Reliability FunctionEnergy Monitoring Related Site Name Set-upPage Number of G-50A se t-up Step Setting Procedure and RestrictionsG-50 Connection Set-up IP address of G-50A se t-up StepSystem Configuration Set-up Monitor the optional functions being used. Procedure2 G-50A data collection Step Unit composition set-up StepChange the unit configuration. Procedure Icon Name Address rangeSe t-up of refrigerant system Step Set-up of group Step Interlocking ventilation unit Interlocked setting StepChange the group No. Procedure Interlocking destination un-set unitMonitoring Screen Set-up Configuration Procedure and RestrictionsSet-up of model name Step Set-up of the number of floors, and floor name Step Creation of a plane view Step Set-up of floor name and G -50Set the group icons on each floor and set their names Set-up of icon arrange and name StepFloor Selection Display Button Group ListSet-up of block Step Set the block groups. ProcedureDeleting block settings Name Change button Block Set button Release buttonChanging the block name Setting Procedures and Restrictions Check before WHM setup. ProcedureModel Baud rate Parity Stop bit Set Charge System options. Procedure Energy Monitoring S e t-upDivision mode for indoor unit Division mode StepDivision mode for outdoor unit Proportiona l division reference dataSelect the OC icon, and click on the selected outdoor unit Delete Watt Hour Meter RelationshipsSet the Indoor Unit and Watt Hour Meter Relationship Relation between indoor units and watt hour meters StepDeleting Watt Hour Meter Relationships Set the charge blocks. Procedure Charge Blocks StepRelease a block from charge blocks Delete the charge blockAdd charge blocks Exit the Currency Settings Selecting a Currency from the Display ProcedureManually Setting the Currency Set the electric power rate schedule. ProcedureSet the standard charge . Procedure 10Standard charge set StepSet the date/time . Procedure Function ContentsTime Set-up Monitor the time Monitor buttonPassword S e t-up Change the passwordNo repair is required Overview Remarks Maintenance Methods and Restrictions Maintenance of Charge DataPreparing for Charging Data Maintenance Display the Maintenance screen. ProcedureUnit Data Maintenance Maintaining Apportioned Unit DataCorrection method Maintenance example Watt Hour Meter Data Maintenance Maintaining watt hour Meter Data ProcedureOperation Amount Data Monitoring Watt hour Meter Monitor Function ProcedureDescription of function Monitoring operation amount data Charge Parameter OutputMonitor the data for the last day after Output file data format Charging RemedyPerforming charging remedy Preparing to perform charging remedy PreparationRemedial apportioning setting screen Apportioning integrated Remark InterValRemedial apportioning confirmation screen Calculating screen Remedy when personal computer HDD fails no backup Remedy when personal computer HDD fails backup Day before recovery day Apportioning method when computer crashes Remedy when watt hour meter fails monitoring impossible Integrate d Remedy for system information setting error Total air-conditioning charge including that Error Code List Air-conditioning unit error codesPage Page System error codes Setting item Case Setting Check ListDetail of function Test Run Check Test run check sheetLRC Date Tester Charging No WHM connection Test Run Check Charging Test Run CheckTest item Comment Page Capacity Check Within Outside Division mode Charge settingSetting TotalExample 1100 conditioner 1300 Outside Within 12001400 Page Page WHM1 WHM2 WHM3 WHM4 WHM5 WHM6 Memo Preparing for Se tup Appendix 1 Installing Windows XP ProfessionalSetup Procedure What you needPage Windows XP Appendix 2 Auto Log-in Confirmation MethodWindows Page WT03901X01