11.2 Test Run Check
Note:
•Before carrying out a test run check, complete the test run checks of the systems under the control of the central controller
•See Chapter 3 for details on site adjustment.
Test run check sheet
Once the initial settings have been carried out as prescribed by the section on field adjustment in this manual, follow the order of testing prescribed by the test run check sheet and check the following items: (1) t o (4).
(1)Check operation start
•Once the necessary information has been entered in the initial screen, advance to the control screen.
•Check that the screen which indicates operation start
•The time depends on the number of air conditioners that are connected. The operation
•Check the display of each floor to make sure there is no error mark.
•If an error occurs, check the error history on the history screen.
(2)
•Operate an air conditioner unit from the
•Confirm the displays of the local remote controller, central controller
•Carry out air conditioner operation in order of group, block, floor and entire building.
•If operation from the
àPosition and name of group icon setting (S ee section 8. 7 . 6)
àIndoor unit and ventilation group setting (See section 8. 6 . 5)
àBlock setting (See section 8. 7 . 7)
(3)Local remote controller
* This step is only required when a local remote controller is connected.
•Operate the air conditioner unit from the local remote controller.
•Confirm the central controller
•On the
(4)Central controller
•Operate the air conditioner unit from the central controller
•Confirm the local remote controller and
•On the
To make the check sheets easy to read, allocate 1 check sheet page for each installation floor unit or central controller
79