4.Flow of Site Adjustment

4.1Flow of Site Adjustment

When the task of site adjustment is subdivided into smaller tasks as shown in the figure below, the tasks can be broadly grouped into three steps. The benefit of following these three steps when carrying out the tasks of site adjustment is that if troubles do arise, it will be clear which step caused the problem. This makes it easier to solve problems and this results in a more efficient execution of site adjustment tasks.

Carry out site adjustment, by following the step by step instructions shown below.

Step 1 G-50A test run

Check that the air conditioners and controllers are correctly configured and that the air con- ditioner works.

Step 2 PC connections and settings

Connect and set up the software and hard- ware on the PC with TG -2000A installed. Check that it is ready for operation.

*For the test operation method of the air conditioner and centralized controller G-50A, refer to the relevant installation manuals.

Check that only the air conditioner test operation has been completed before starting Step 1.

*See Chapter 4 in this booklet for details.

Step 3 TG-2000A system test run

Check that the TG -2000A man-machine system can correctly operate air conditioner units of all the managed systems by issuing TG -2000A commands.

HUB

LAN Integrated centralized

control software TG-2000A

Step 2

Step 3

Power

supply unit

G- 50A

Step 1

Step 1

4.2Tools for Site Adjustment

You will need the following equipment and reference material in order to easily carry out site adjustment. <Measurement instruments>

• Tester: to check the wiring and the voltage <Reference material>

All necessary drawings of the air conditioning control system

TG-2000A Instruction Manual (Site Adjustment (this manual), Management)

Operation Manual for each air conditioner unit and controller

<Ot her material>

 

Floppy disk

: used when copying data

CD-R

: used to store generated data and copy it to the site PC.

Initial setting tool: Personal computer in which this tool is installed

LAN cable

: PAC-YG00FA LAN cable

Screwdriver kit

Other usual maintenance tools

6

Image 9
Contents Please keep this manual for future use Please read this manual before using the unitContents Page Safety Precautions Other machinesDo not use with other applications System Requirements Requirements system recommendations Compatible Units¡ *1 Restrictions Number of unitsRestrictions M e Manufacturer Model Other DevicesHardware Connection Diagram System Configuration System Configuration ExampleTools for Site Adjustment Flow of Site AdjustmentPC connections and settings 50A test runD e l s IP address range Test operation from centralized controller G-50APage G-2000A Setup InstallationPreparing for installation Steps Action Details How toMsde setup Running TG-2000A Setup New setupDatabase setup When the installation is completed, restart the computerInstallation start confirmation Check the installation folderTG-2000A setup completion Read the license agreementG-2000A Uninstall TG-2000A uninstallMsde uninstall Part Names and Functions Window Elements Basic Mouse Operation Accessing Functions and Moving between WindowsShift from the initial window to the control window Shift from the control window to the initial windowPage Page User Set -up Set TG -2000A functions Page Page Startup Initial Startup and Shutdown Before StartupShutdown TG-2000A ShutdownShutting down the OS System Setting Procedure System Setting Procedure System Setting ScreenGeneral Operation User Set-upReliability Function Connection SettingSite Name Set-up Energy Monitoring RelatedPage G-50 Connection Set-up Setting Procedure and RestrictionsNumber of G-50A se t-up Step IP address of G-50A se t-up StepMonitor the optional functions being used. Procedure System Configuration Set-upUnit composition set-up Step 2 G-50A data collection StepIcon Name Address range Change the unit configuration. ProcedureSe t-up of refrigerant system Step Set-up of group Step Change the group No. Procedure Interlocked setting StepInterlocking ventilation unit Interlocking destination un-set unitConfiguration Procedure and Restrictions Monitoring Screen Set-upSet-up of model name Step Set-up of the number of floors, and floor name Step Set-up of floor name and G -50 Creation of a plane view StepFloor Selection Display Button Set-up of icon arrange and name StepSet the group icons on each floor and set their names Group ListDeleting block settings Set the block groups. ProcedureSet-up of block Step Name Change button Block Set button Release buttonChanging the block name Check before WHM setup. Procedure Setting Procedures and RestrictionsModel Baud rate Parity Stop bit Energy Monitoring S e t-up Set Charge System options. ProcedureDivision mode for outdoor unit Division mode StepDivision mode for indoor unit Proportiona l division reference dataDelete Watt Hour Meter Relationships Select the OC icon, and click on the selected outdoor unitRelation between indoor units and watt hour meters Step Set the Indoor Unit and Watt Hour Meter RelationshipDeleting Watt Hour Meter Relationships Charge Blocks Step Set the charge blocks. ProcedureDelete the charge block Release a block from charge blocksAdd charge blocks Manually Setting the Currency Selecting a Currency from the Display ProcedureExit the Currency Settings Set the electric power rate schedule. Procedure10Standard charge set Step Set the standard charge . ProcedureFunction Contents Set the date/time . ProcedureTime Set-up Monitor button Monitor the timeChange the password Password S e t-upNo repair is required Overview Remarks Preparing for Charging Data Maintenance Maintenance of Charge DataMaintenance Methods and Restrictions Display the Maintenance screen. ProcedureMaintaining Apportioned Unit Data Unit Data MaintenanceCorrection method Maintenance example Maintaining watt hour Meter Data Procedure Watt Hour Meter Data MaintenanceWatt hour Meter Monitor Function Procedure Operation Amount Data MonitoringDescription of function Charge Parameter Output Monitoring operation amount dataMonitor the data for the last day after Charging Remedy Output file data formatPerforming charging remedy Preparation Preparing to perform charging remedyApportioning integrated Remark InterVal Remedial apportioning setting screenRemedial apportioning confirmation screen Calculating screen Remedy when personal computer HDD fails no backup Remedy when personal computer HDD fails backup Day before recovery day Apportioning method when computer crashes Remedy when watt hour meter fails monitoring impossible Integrate d Remedy for system information setting error Total air-conditioning charge including that Air-conditioning unit error codes Error Code ListPage Page System error codes Setting Check List Setting item CaseDetail of function Test run check sheet Test Run CheckLRC Date Tester Charging Test Run Check Charging No WHM connection Test Run CheckTest item Comment Page Capacity Setting Division mode Charge settingCheck Within Outside TotalExample 1100 conditioner 1300 Outside Within 12001400 Page Page WHM1 WHM2 WHM3 WHM4 WHM5 WHM6 Memo Setup Procedure Appendix 1 Installing Windows XP ProfessionalPreparing for Se tup What you needPage Appendix 2 Auto Log-in Confirmation Method Windows XPWindows Page WT03901X01