Chapter 3 Installing the Cisco uBR7225VXR Router

Configuring the Interfaces

At any point you may enter a questions mark ‘?’ for help.

Use ctrl-c to abort configuration dialof at any prompt.

Default settings are in square brackets ‘[]’.

continue with configuration dialog? [yes]:

You can proceed with the setup facility or exit from the setup facility, using the command interface to configure global (system-wide) and interface-specific parameters.

Caution The setup facility currently excludes cable-specific configuration commands. Upstream ports, therefore, have a default state of “shutdown” after the setup facility is run. You must configure upstream parameters. For additional information, refer to the Cisco uBR7200 Series Software Configuration Guide at the following URL:

http://www.cisco.com/en/US/docs/cable/cmts/ubr7200/configuration/guide/cr72scg.html

You do not have to configure the interfaces immediately; however, you cannot enable the interfaces or connect them to any networks until you have configured them.

Many of the cable interface line card LEDs do not come on until you have configured the interfaces. To verify correct operation of each interface, complete the first-time startup procedures and configuration, then refer to the document for each cable interface line card for LED descriptions and to check the status of the interfaces.

Your Cisco uBR7225VXR chassis installation is complete. To set up your cable network headend, proceed to Chapter 4, “Connecting the Cisco uBR7225VXR Router to the Cable Headend.” To begin configuring your Cisco uBR7225VXR router, see the Cisco uBR7200 Series Software Configuration Guide at the following URL:

http://www.cisco.com/en/US/docs/cable/cmts/ubr7200/configuration/guide/cr72scg.html

 

Cisco uBR7225VXR Universal Broadband Router Hardware Installation Guide

3-20

OL-17309-02

Page 70
Image 70
Cisco Systems UBR7225VXR specifications OL-17309-02