Installation

11.Insert and begin tightening two (2) hex head bolts with one washer each through bracket mounted at front of cabinet into anchor inserts in mounting surface (see Figure 23).

Figure 23 Mounting front bolts—front side of cabinet

12.Check the bubble level on the floor of the cabinet on the right hand side of the Power Conversion Module (see Figure 24). The Liebert FS is sufficiently level when the bubble is within the outer of the two circles. If the bubble is outside the outer circle, use the leveling feet to adjust until bubble is within the outer circle.

Figure 24 Bubble level

Bubble level

13.Once the cabinet is level, firmly tighten the front bolts to drop-in anchors as shown in Figure 134. The front bolts must be tightened to 40 foot-pounds (54 N-m) of torque.

23

DISCONTINUED

 

PRODUCT

Page 35
Image 35
Emerson 540VDC manual Mounting front bolts-front side of cabinet, Bubble level