AI232 Version 9.6x User’s Guide
Product Description: Distribution Panels
1-11
Installation Procedure
1. Attach the mounting flanges and tie bar as shown in Figure 1-5. (Table 1-4 shows
the part list.)
2. Install the distribution panel to the rack. Figure 1-6 shows a typical installation.
Figure 1-5 DP232-RJ45 Distribution Panel
PORTS 1 - 8
PORTS 17 - 24
PORTS 9 - 16
PORTS 25 - 32
1458912
17 20 21 24 25 28
13 16
29 32
DP232-RJ45
WWW.AIINET.COM
Install the mounting flanges in
the desired location
Setting flanges for a 19-inch rack Setting flanges for a 23-inch rack
Install the mounting flanges in
the desired location
5
13
5
13
4
4
Table 1-4 Parts List
Item Description Part No. Quantity
1 Tie Bar 06-410-002 1
2 Mounting Flange (left side) 06-110-003 1
3 Mounting Flange (right side) 06-110-005 1
4 #6-32 Screw with lockwasher 00-018-001 6
5 #12-24 Screw with lockwasher 00-015-003 2