38 Chapter 4 Installing the R2MFC MBM

Reconnecting the equipment

After you install the module correctly into the bay, you must return the equipment to operation.

Caution: Complete the following steps carefully to ensure you return your system to operation without endangering the equipment or yourself.

1Plug the power cords for the BCM and any expansion units back into the AC outlets.

Note: The Business Communications Manager system starts up when you connect the AC power cord. System startup takes several minutes to complete.

2Connect the cables to the proper outlets on the R2MFC MBM and the MSC on the BCM.

3Check that the LEDs on the newly installed R2MFC MBM are on and indicating the correct state. Refer to “Faceplate LEDs” on page 66 for a detailed description of the LED states.

4Confirm that the BCM is functioning properly by testing to make sure it works the same as it did before installing the R2MFC MBM.

5Configure the module. Refer to Chapter 5, “Configuring the R2MFC MBM,” on page 45 for details.

Removing an R2MFC MBM

Follow the procedures in this section to remove an R2MFC MBM from a BCM platform base chassis or expansion unit.

Figure 10 provides an overview of the process for removing an R2MFC MBM.

Figure 10 Overview of removing an R2MFC MBM

Shut down BCM and expansion unit

Disconnect power from

both units

Remove module cables

Remove module