Task 016: Testing Data Connectivity

2. BitStorm 1900 Installation and Testing

Task 016: Testing Data Connectivity

This procedure checks data connectivity from the customer premise distribution frame and the BitStorm 1900 shelf.

Requirements

A StormPort Modem with power adapter and extension cord (if necessary) is required for this procedure.

Step Procedure

1.) Identify the data connections being tested at the EtherLoop cross- connect block and the Modem card on the BitStorm 1900 shelf.

2.) Install and connect the modems on the corresponding lines at the customer premises locations.

3.) Connect power to the modem.

4.) Turn on the BitStorm 1900.

5.) Observe the modem and BitStorm 1900 Modem card LEDs. After about 4-5 minutes, all LEDs at both the BitStorm 1900 and CPE locations should be green, with the transfer LEDs flickering.

STOP

<RX￿KDYH￿FRPSOHWHG￿WKLV￿WDVN￿

2-100

BitStorm 1900 Installation and Maintenance Guide

1900-A2-GN20-00

Page 116
Image 116
Paradyne 1900 manual Task 016 Testing Data Connectivity, Step Procedure