2. BitStorm 1900 Installation and Testing
Task 011: Installing External Voice Switch Connections
Use this procedure to connect the BitStorm 1900 lines to an external voice facility.
Requirements
This procedure requires the following tools and materials:
•24 jumper wires
•
"Appendix B. Cabling Specifications," on page 115 contains the specifications for the cables and wiring required in this procedure.
Step Procedure
1.) Identify the existing Tip and Ring jumper connections from the external voice facility
2.) Verify dial tone on the existing voice facility at the CPE cross- connect block for the line being rerouted.
3.) Remove the Tip and Ring jumper connections from the line.
4.) Terminate the Tip/Ring jumper wires from the
5.) Terminate the jumper wires from the CPE Tip/Ring connections to the "EtherLoop" side of the
6.) Verify the new connection by testing dial tone again at the CPE
7.) Secure all cabling in accordance with local office procedures.
BitStorm 1900 Installation and Maintenance Guide |
|