2. BitStorm 1900 Installation and Testing

Task 001: Pre-Installation Checklist

Before installing the BitStorm 1900 system, verify that the following steps have been completed:

Step Procedure

1.) Perform site survey and verify equipment bays are installed correctly.

2.) Verify that the amount of rack space is adequate for the required installed application.

3.) Verify the racks are secured and electrically grounded according to standard industry practice. Refer to "Appendix A. Installation Requirements," on page 107 for specifications.

4.) Verify you have all necessary tools, equipment, and materials for the installation. Use the following table as a guide

Table 2-8: Installation Tools, Equipment, and Materials

Tools, Equipment, and Materials

Installation hardware kit supplied with shelf

Phillips-head screwdriver (#1 or #2)

Anti-static protection such as a grounded wrist strap

Volt-ohm meter

PC with serial port to configure MIU

Cross-connect punch-down tool

14-gauge stranded cable

Cable ties

5 BitStorm 1900 cable harnesses

5 intermediate cables

Cross-connect block(s) of the same type used in the existing main distribution frame (MDF)

24 AWG Jumper Wires (24 wires per modem card)

2-36

BitStorm 1900 Installation and Maintenance Guide

1900-A2-GN20-00

Page 52
Image 52
Paradyne 1900 manual Task 001 Pre-Installation Checklist, Installation Tools, Equipment, and Materials