2. BitStorm 1900 Installation and Testing
Task 001: Pre-Installation Checklist
Before installing the BitStorm 1900 system, verify that the following steps have been completed:
Step Procedure
1.) Perform site survey and verify equipment bays are installed correctly.
2.) Verify that the amount of rack space is adequate for the required installed application.
3.) Verify the racks are secured and electrically grounded according to standard industry practice. Refer to "Appendix A. Installation Requirements," on page 107 for specifications.
4.) Verify you have all necessary tools, equipment, and materials for the installation. Use the following table as a guide
Table 2-8: Installation Tools, Equipment, and Materials
Tools, Equipment, and Materials
Installation hardware kit supplied with shelf
PC with serial port to configure MIU
Cable ties
5 BitStorm 1900 cable harnesses
5 intermediate cables
24 AWG Jumper Wires (24 wires per modem card)
BitStorm 1900 Installation and Maintenance Guide |
|