2. BitStorm 1900 Installation and Testing
Task 008: Installing Voice/Data & Filter Shelf Connections
Use this procedure to connect the BitStorm 1900 to the EtherLoop
Requirements
This procedure requires the following tools and materials:
•10 BitStorm 1900 cable harnesses
•10 intermediate cables
•10 BitStorm 1900 data cables
"Appendix B. Cabling Specifications," on page 115 contains the specifications for the cables and wiring required in this procedure.
Step Procedure
1.) Place and secure the dedicated EtherLoop
2.) Designate and label one side of each block as "Line/CPE," and the other side as "Voice."
3.) Review pin and pair assignments in Figure
BitStorm 1900 Installation and Maintenance Guide |
|