2. BitStorm 1900 Installation and Testing

Installation Task List

The following is a complete list of all tasks to perform. To install the

BitStorm 1900 complete each task in the order given.

Task # and Description

Page

 

 

 

 

Task 001: Pre-Installation Checklist

36

 

 

Task 002: Installing the 19” Fan Tray

38

 

 

Task 003: Installing the BS1900 and Filter Shelves

42

 

 

Task 004: Installing the Air Baffle

47

 

 

Task 005: Installing the Circuit Packs

48

 

 

Task 006: Connecting Power to the Shelf

49

 

 

Task 007: Installing the Data Network Connection with an MIU

54

 

 

Task 008: Installing Voice/Data & Filter Shelf Connections

58

 

 

Task 009: Installing Voice/Data w/Filter 66-Block Connections

64

 

 

Task 010: Installing the Data-only Connections

67

 

 

Task 011: Installing External Voice Switch Connections

70

 

 

Task 012: Configuring the MIU

72

 

 

Task 013: Configuring Remote Management

87

 

 

Task 014: Testing the BitStorm 1900 Installation

96

 

 

Task 015: Testing Voice Connectivity

99

 

 

Task 016: Testing Data Connectivity

100

 

 

Task 017: EtherLoop End-to-End Testing

101

 

 

Installing the BitStorm 1900

The following tasks and procedures have been provided to properly install the BitStorm 1900 components. The installation is organized into numbered tasks with each task containing all of the procedural steps for completion. Complete each task in the order given and complete each step for a task procedure in the order given before continuing on to the next task.

1900-A2-GN20-00

BitStorm 1900 Installation and Maintenance Guide

2-35

Page 51
Image 51
Paradyne 1900 manual Installation Task List, Installing the BitStorm, Task # and Description