SOLA 4000 - Installation and Initial Start-Up

1 Installation

1 INSTALLATION

1.1 Mechanical Installation

Equipment Delivery and Storage After delivery, check equipment for any damage that may have occurred during shipment. The shipper and your SOLA agency must be notified in writing about damages due to shipment, includ- ing a detailed description of visual defects. If you do not wish to install the equipment immediately, please observe the following storage recommendations:

Store equipment in a vertical position in a well conditioned room, protected against humidity. Do not store the equipment in close proximity to frequently used passageways and keep it away from movable parts.

If the UPS system is already unpacked, please ensure storage in a clean environment protected from dust, away from heat sources.

Handling the UPS System The UPS can be simply lifted and moved by means of a lifting truck or a fork lifter for 80-120kVA units. For 10-60kVA units, remove the front side and rear side base sheets and attach two angle irons with 8MA bolts to the right front and rear side of the UPS. The UPS can now be moved with a lifting fork. Remove the angle irons when the UPS is set in the correct position.

Caution: Secure equipment against being knocked over

Setting Up The UPS system should be installed in a dry, clean and lockable room. Provisions have to be made to remove heat created by the system. Under all installation conditions, the unrestricted flow of cooling air must be assured.

JUE 401265