SOLA 4000 - Installation and Initial Start-Up

1 Installation

1.2 Electrical Installation

This equipment must be installed by qualified service person- nel.

Switch off IRP, IRE, IB, IUG, IBY circuit breakers to completely isolate the equipment.

Earth leakage protection: this device has high leakage current towards protective earthing. Earth leakage circuit breakers shouldn't be installed upstream from this equipment or a correct threshold should be set.

High leakage current - it is essential to connect the protective earth before connecting the power supply.

All primary power switches installed remotely from the UPS area must be fitted with the following label: "Isolate uninterruptible power supply (UPS) before working on this circuit".

General

All electrical connections must be made in accordance with local standards and all input terminals (1-L1, 1-L2, 1-L3 and, if existing, 4-L1, 4-L2, 4-L3) must be protected by external fuses. The tables give recommended values for fuse sizes and cable cross-sections. These may vary, depending on local standards. They are valid for voltages 380/220 V, 400/230 V and 415/240 V. Ensure clockwise connection of conductors L1, L2 and L3 at input and output termi- nals.

If possible, install battery cables separately from other power cables in order to avoid possible RF interference. Before wiring, open all system switches (IRP, IRE, IBY, IUG) plus the battery switch (IB).

JUE 401265

20

Page 20
Image 20
Powerware SOLA 4000 manual Electrical Installation, General