Powerware SOLA 4000 manual System START-UP has NOW Been Successfully Completed

Models: SOLA 4000

1 108
Download 108 pages 42.07 Kb
Page 56
Image 56

SOLA 4000 - Installation and Initial Start-Up

3 Additional Start-Up Proced. for Multi-Unit Systems

to the nominal load. Measure the currents at the output of each module on phase T. If this current varies by more than ± 1% for this module, fine adjustment can be made with P1 on the IPR pcb.

Check the currents at the output of each module on phase S. These currents must be balanced to within ± 1% by finely adjusting the inverter voltage of phase S (P4 on ICT-2). i.e. If the module is supplying more current than the system average, the inverter voltage of this module must be reduced slightly.

Repeat for phase R currents by finely adjusting the R phase inverter voltage of this module with P3 on the ICT-2 pcb until the currents on the phase R of all modules are equal to within

± 1%.

THE SYSTEM START-UP HAS NOW BEEN SUCCESSFULLY COMPLETED.

JUE 401265

56

Page 56
Image 56
Powerware SOLA 4000 manual System START-UP has NOW Been Successfully Completed