INSTALLATION

SECTION 3-8

TEST THE ZERO SPEED SENSOR

{Continued from previous page)

Screen Cradle Jackscrew

Push the start button to start the granulator

When the machine reaches full speed, push the stop button to stop the granulator.

Open the screen cradle interlock using the procedure in Section 6-4 entitled Screen Replacement.

Release the cradle retainers using the procedure in Section 6-9 entitled Screen Replacement.

While the rotor is still turning, actuate the screen cradle hydraulic cylinder or jackscrew from the control console by turning the CC/screen cradle selector switch to the LOWER POSITION.

The hydraulic cylinder or jackscrew should NOT operate until the rotor has come to a complete stop.

If the hydraulic cylinder or jackscrew operates before the rotor stops, TURN OFF AND LOCKOUT THE POWER per OSHA 1910.147 OR ANSI Z244.1-1982 (Lockout/Tag-out of Energy Sources).

LUBRICATION

The machine is pre-lubricated except for the motor. For motor lubrication, check the tag supplied by the motor manufacturer.

After the BP2400 Series Granulator has been in service for some time, the jackscrews and the main bearings should be lubricated periodically.

Refer to Section 6, Maintenance, for further information.