Application – All Motors
Use of Engine Driven Generators - Single-Phase or Three-Phase
Table 5 lists minimum generator sizes based on typical 80 °C rise continuous duty generators, with 35% maximum voltage dip during starting, for Franklin’s three- wire motors, single- or
This is a general chart. The generator manufacturer should be consulted whenever possible, especially on larger sizes.
There are two types of generators available: externally and internally regulated. Most are externally regulated. They use an external voltage regulator that senses the output voltage. As the voltage dips at motor
Internally regulated
Generators must be sized to deliver at least 65% of the rated voltage during starting to ensure adequate starting torque. Besides sizing, generator frequency is important as the motor speed varies with the frequency (Hz). Due to pump affi nity laws, a pump running at 1 to 2 Hz below motor nameplate frequency design will not meet its performance curve. Conversely, a pump running at 1 to 2 Hz above may trip overloads.
Generator Operation
Always start the generator before the motor is started and always stop the motor before the generator is shut down. The motor thrust bearing may be damaged if the generator is allowed to coast down with the motor running. This same condition occurs when the generator is allowed to run out of fuel.
Follow generator manufacturer’s recommendations for
Table 5 Engine Driven Generators
NOTE: This chart applies to
MOTOR RATING |
| MINIMUM RATING OF GENERATOR |
| ||||
HP | KW | EXTERNALLY REGULATED | INTERNALLY REGULATED | ||||
KW | KVA | KW | KVA | ||||
|
| ||||||
1/3 | 0.25 | 1.5 | 1.9 | 1.2 |
| 1.5 | |
1/2 | 0.37 | 2 | 2.5 | 1.5 |
| 1.9 | |
3/4 | 0.55 | 3 | 3.8 | 2 |
| 2.5 | |
1 | 0.75 | 4 | 5.0 | 2.5 |
| 3.13 | |
1.5 | 1.1 | 5 | 6.25 | 3 |
| 3.8 | |
2 | 1.5 | 7.5 | 9.4 | 4 |
| 5 | |
3 | 2.2 | 10 | 12.5 | 5 |
| 6.25 | |
5 | 3.7 | 15 | 18.75 | 7.5 |
| 9.4 | |
7.5 | 5.5 | 20 | 25.0 | 10 |
| 12.5 | |
10 | 7.5 | 30 | 37.5 | 15 |
| 18.75 | |
15 | 11 | 40 | 50 | 20 |
| 25 | |
20 | 15 | 60 | 75 | 25 |
| 31 | |
25 | 18.5 | 75 | 94 | 30 |
| 37.50 | |
30 | 22 | 100 | 125 | 40 |
| 50 | |
40 | 30 | 100 | 125 | 50 |
| 62.5 | |
50 | 37 | 150 | 188 | 60 |
| 75 | |
60 | 45 | 175 | 220 | 75 |
| 94 | |
75 | 55 | 250 | 313 | 100 |
| 125 | |
100 | 75 | 300 | 375 | 150 |
| 188 | |
125 | 90 | 375 | 469 | 175 |
| 219 | |
150 | 110 | 450 | 563 | 200 |
| 250 | |
175 | 130 | 525 | 656 | 250 |
| 313 | |
200 | 150 | 600 | 750 | 275 |
| 344 |
WARNING: To prevent accidental electrocution, automatic or manual transfer switches must be used any time a generator is used as standby or back up on power lines. Contact power company for use and approval.
Use of Check Valves
It is recommended that one or more check valves always be used in submersible pump installations. If the pump does not have a
be used.
Swing type check valves are not acceptable and should never be used with submersible motors/pumps. Swing type check valves have a slower reaction time which can cause water hammer (see next page). Internal pump check valves or spring loaded check valves close quickly and help eliminate water hammer.
Check valves are used to hold pressure in the system when the pump stops. They also prevent backspin, water
hammer and upthrust. Any of these can lead to early pump or motor failure.
NOTE: Only positive sealing check valves should be used in submersible installations. Although drilling the check valves or using
A.Backspin - With no check valve or a failed check valve, the water in the drop pipe and the water in the system can fl ow down the discharge pipe when the motor stops. This can cause the pump to rotate in a reverse direction. If the motor is started while it is backspinning, an excessive force is placed across the
B.Upthrust - With no check valve, a leaking check valve, or drilled check valve, the unit starts under
5