A-BOOM PRE-DELIVERY INSPECTION CHECKLIST
Saftey Equipment:
-----Operators Manual is with Unit.
-----The Safety Decals are installed as listed in the Assembly Manual.
-----Valve operation plate is installed.
-----Operators cage or Tractor Cab is in place. (Item 1 page
-----Deflectors are installed on the Mower Head. (Item 2 page
-----Tractor Rops or Cab with seatbels installed properly.
Frame and Boom:
-----Axle Plate Bolts are torqued to 240 ft. lbs. (Item 3 page
-----Boom Rest Axle Plate Bolts are torqued to 240 ft. lbs.
-----Front Rail Bolts are torqued to 170 ft. lbs. (Item 17 page
-----Front Support Bolts are torqued to 240 ft. lbs. (Item 4 page
-----Hydraulic Tank mounting Pins / Bolts in place correctly.
-----Boom Main Pins are torqued to 170 ft. lbs.
-----King Pin Retaining Nut is properly locked in place.
-----All Welds inspected toinsure proper welds and locations.
Hydraulic System:
-----Oil Level in Hydraulic Tank is within the sight gauge. (Item 5 page
-----Hose connections are tightented according to specifications.
-----Hoses do not have any kinks or twist in them.
-----Front Pump Shaft adapter bolts are tight. (Item 6 page
-----Front Pump Shaft Coupler / Drive Shaft is lubricated and has an
-----The Pump Drive Shaft has correct alignment.
-----Suction Hose has no leaks or kinks.
Rotary Mower Head:
-----Skid Shoe Bolts are torqued to 120 ft. lbs. (Item 8 page
-----Spindle Housing Bolts are torqued to 400 ft. lbs. (Item 9 page
-----The Spindle Housing is properly lubricated. (item 10 page
-----Motor Bolts are torqued to 120 ft. lbs. (Item 11 page
-----Blade Carrier (Bar) Bolts torque to 400 ft. lbs. (Item 12 page
-----All Blade Bolts are torqued, the retainings Pins are in place. (item 13 page
-----Blades Swing freely. (Item 14 page