Frame Rail Installation 4 WD
Re-Install High Frame to Tractor: (continued)
8.Tighten All Frame Mounting Bolts. Tighten all the Frame Mounting bolts that have only be snugged till now. Go through and make sure none are missed.
A.Front Mounting Pad Bolts. There are 4 Bolts on each Pad the LH and RH, 8 Total (See Figure 22).
B.Frame Stiffener Crossmember. There are 2 bolts on each side or 4 total. Make sure these bolts have been installed with the nuts on top.
(See Figure 23).
C.Frame Rails to Rear Axles. The Rear of the frame rails bolt up to the Bottom of the Tractor Axle Housing. There is also an Axle Strap on each side which has long bolts through them from Axle Strap on top down and through the Frame rail Mount Plate. The RH side also has the Boom rest bolted on with it and the Axle Strap bolts go through it. Tighten all of these bolts at the rear axle of tractor. (See Figure 24 & 25).
D.Check all Bolts for Tightness. Check to make sure all Frame Mounting bolts and nuts have been tightened, Also inspect to make sure they are installed correctly (See Figures 1 through 27).
Tighten LH & RH
Side
Tighten LH & RH
Side
Figure 22
Tighten LH & RH
Side
Figure 23
Tighten LH & RH
Side
Figure 24
Figure 25
© 2003 Alamo Group Inc. | Section 5- 7 |