Frame Rail Installation
Tack Welding Frame Rails: (continued)
4.Frame Stiffener Assembly. The frame stiffener is an assembly designed to run under the Tractor to tie the two Frame Rails together and support each other. The Gusset Rail Support is designed to stabilize the Frame Rails to the tractor frame.
| Vertical Tube of RH Frame Rail | |
Front Wheel End |
| |
|
| |
|
| Rear Axle End |
Tack Weld here on both |
| Horizontal Tube |
sides Front and Back only |
| Gusset Rail Support |
after alignment |
| |
|
| |
Align Flush with Bottom |
| Tack Weld Here |
| after final | |
of Vertical Tube |
| assembly only |
RH Rail Stiffener Weldment (RH Side) |
| |
Rail Stiffener Tube Crossmember |
| |
|
| LH Frame Rail is |
LH Rail Stiffener Weldment | Mounted Here | |
Figure 39 | (LH Side) |
|
|
|
5.Locate Mounting Tubes and Hardware. See Figure 31 for breakdown of these components.
A.There will be one Mounting Tube for each side; these tubes are the same so it will not matter which is on which side. The Mounting Tubes are the same on either end. (See
Figure 31 - Item 1).
B.There will be 8 Bar Mounting Straps (Part # 02966639); these straps are the same but later in the assembly process 2 will have to be cut (See Figure 31 - Item 2 & 2A).
C. | There are 2 Angle Mounts (Part # 02966641), these have two holes in them and when |
| mounted the hole will be up. (See Figure 31 - Item 5). |
D.There are 8 bolts (Part # 02957039) & Locknuts (Part # 00037200), the bolts are 3/4" X
© 2003 Alamo Group Inc. | Section 4 - 18 |