1 | 2 | 3 | 4 | 5 | 6 | 7 | WAN |
1 | To host | 4 | Library controller card terminator connection |
2 Master to cartridge elevator | 5 | 10BaseT connections | |
3 | Cartridge elevator to secondary master |
|
|
Figure 85. Four module library cabling
2.Install a terminator on the master library controller adapter connection.
3.Optional: Connect the WAN point to the host with a 10BaseT cable as shown in Figure 64 on page 71 and Figure 85. This step is applicable to systems that utilize a host. (For WEB TLC operations.)
4.Using 10BaseT cable, connect a cable from router port 1 to the primary master SDLT module. See Figure 64 on page 71 and Figure 85.
5.Connect a cable from router port 2 to the secondary master.
6.Continue connecting cables, router port 3 to the third module, port 4 to the fourth module and so on until all modules are connected to the router. Ensure the power is off before proceeding with steps 7 and 8.
864560SLX Tape Library: User’s Guide