Single Module UPS Installation
1.6Power Cables
The cable design must comply with the voltages and currents provided in this section, follow local wir- ing practices and take into consideration the environmental conditions (temperature and physical support media).
For cable entry terminal, refer to Figure 22.
! WARNING
Before starting the UPS, ensure that you are aware of the location and operation of the external isolators that connect the ups input/bypass supply to the mains distribution panel.
Check that these supplies are electrically isolated and post any necessary warning signs to prevent their inadvertent operation.
! WARNING
Failure to follow adequate earthing procedures may result in electromagnetic interference or in hazards involving electric shock and fire.
Table 1 | Maximum steady state AC and DC currents |
|
|
|
| ||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Nominal Current, Amps |
|
|
| Busbar Stud Size |
| |||||
|
|
|
|
|
|
|
|
|
|
|
| ||||
| Input Mains Current 1,2 | Output Current2 |
| Input/Output/ |
|
|
| ||||||||
| With Full Battery |
|
|
|
| ||||||||||
|
| Recharge |
| at Full Load |
| Bypass |
|
|
| ||||||
|
|
| 3ph + N |
|
| 3ph + N |
|
| Cables | External |
|
| |||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
UPS |
|
|
|
|
|
|
|
|
| Battery at |
| Hole | battery |
| Torque |
Rating |
|
|
|
|
|
|
|
|
| End of |
| Dia. | Cables |
| Load |
(kVA) | 380V |
| 400V |
| 415V | 380V | 400V |
| 415V | Discharge | Bolt | (mm) | (Bolts) |
| (Nm) |
10 | 22 |
| 21 |
| 20 | 15 | 14 |
| 13 | 22 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15 | 33 |
| 32 |
| 31 | 22 | 21 |
| 20 | 33 | M6 | 6 | M6 |
| 5 |
|
|
|
|
|
|
|
|
|
|
|
| ||||
20 | 44 |
| 43 |
| 42 | 30 | 29 |
| 28 | 44 |
| ||||
|
|
|
|
|
|
|
| ||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
30 | 63 |
| 62 |
| 61 | 45 | 44 |
| 42 | 66 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.Input mains current listed for common rectifier and bypass AC input. For split input the rectifier current is 94% of the currents listed.
2.
3.Protective earth cable: Connect each cabinet to the main ground system must follow the most direct route possible.
The earth conductor shall be sized in accordance with the AC supply fault rating, cable lengths and type of protection. Typical cross sectional areas are 2.5mm2 (10kVA), 6mm2 (15kVA), 10mm2 (20kVA), 16mm2 (30kVA), as per AS / IEC
4.When sizing battery cables, a maximum volt drop of 4 VDC is permissible at the current ratings given in Table 1. The load equipment is generally connected to a distribution board containing individually protected busbars rather than connected directly to the UPS output. The output cables from paralleled units to the parallel distribution bus should be of same length so as to optimise the sharing of current. Do not form coils, so as to minimise the formation of electromagnetic interference.
5.For terminal location – refer to 4.0 - Installation Drawings)
Table 2 Distance from floor to connection point on the equipment
| Minimum Distance |
UPS | mm (in.) |
|
|
Rectifier A.C. Input supply | 284 |
|
|
Bypass A.C. Input supply | 284 |
|
|
UPS Output A.C. | 369 |
|
|
Battery Power | 369 |
|
|
Auxiliary cables: Monitor board (U2) | 1104 |
|
|
8