Premier Floors Where walls terminate against a panel, you can drill at the horizontal electrical

Page 34
Where walls terminate against a panel

Push or pull all wires through a chase simultaneously. With an electrician’s pliers fold and crimp the longest wire back on itself about 1”. Wrap electrical tape around that end. Stagger remaining wires flat side to flat side and tape these to the long wire below the crimp. Have 8”–10” of straight wire to slide into the electrical chase holes.

As a general rule, don’t try to go horizontal between outlets or switches in the panels unless the distance is short and you have no other options. Use the vertical chases to run the wire back into the floor or roof cavities. Run the wires horizontally in these areas to access the vertical chases in the panels.  

To gain access to chase intersections, use a 4” to 4 1/8” hole saw. Use a flat blade screw driver and pry out the plug. Nail the plug to the wall for reinstallation.

After pulling your wires, secure the plug with Premier Mastic or expanding foam.

Where walls terminate against a panel

you can drill (at the horizontal electrical

chase height) a long diagonal hole through the face of the stud diagonally into the electrical chase. Electrical wires will stuff easily into this type of access.

34

Image 34
Contents installation guide Introduction Table of Contents PBS SIPs Tips Do not put plumbing inside SIPs Fill all voids with expanding foamStorage & Handling Checklist of Tools Spline Connection Lumber Connection I-JoistConnection Panel Basics - Assembly Fasteners Field FabricationPage Field Fabrication Rake/Gable Walls Floors Page PANEL TIP Stagger your panel placement with two panels on one side of the beam, four panels on the other side, and four back on the first side of the beam. This will help your beam stay straight Sill Plates Page Walls STEP 2. LAYOUT TRANSFER STEP 3. PANEL TILTSTEP 4. ADJACENT PANEL STEP 5. FASTENING STEP 6. TOP PLATEHeaders Page Intermediate Floors Page Roofs On the Ground Lifting PanelsPage Page Insul-Lam Electrical Where walls terminate against a panel you can drill at the horizontal electricalPlumbing Shearwalls Premier Panel R-Values Panel Core Panel Core Panel Span ft Panel Core Panel Core Panel Core Panel Core Load Chart Header Header Premier Insul-BeamIIHeader Loads Load ChartNo. of Panel Panel Minimum Load Chart 12 Wind Pressure Chart 1 ofSpeed Load Chart 12 Wind Pressure Chart 2 ofSpeed Page SOUTHWEST REGIONAL FIELD OFFICES NORTHWEST4609 70th Ave. East Fife, WA 3434 W. Papago St. Phoenix, AZ