Premier Floors manual Panel

Page 50
Panel

50

Panel

Minimum

 

Attachments

 

 

Shear

OSB Face

2x Framing

 

Splines

Type

 

(plf)

Thickness

 

 

 

 

 

 

Fasteners

Spacing

Fasteners

 

Spacing

 

 

 

 

 

 

 

 

 

L or S

7/16”

8d box nail

6 inches

8d nail

 

6 inches

300

 

 

 

 

 

 

 

 

S

7/16”

8d box nail

4 inches

#6 screw3

 

4 inches

6004

 

 

 

 

 

 

 

 

1.Framing lumber shall be a minimum of SPF #2 having a minimum specific gravity of 0.43.

2.The maximum panel height-to-width ratio shall be 3.5:1

3.Screws are #6 x 1-1/4 inch Type W drywall screws.

4.Two top plates are required.

Load Chart 10A:

Premier Wall SIPs1,2 Maximum

Allowable Shear Wall Loads

Image 50
Contents installation guide Introduction Table of Contents PBS SIPs Tips Do not put plumbing inside SIPs Fill all voids with expanding foamStorage & Handling Checklist of Tools Spline Connection Lumber Connection I-JoistConnection Panel Basics - Assembly Fasteners Field FabricationPage Field Fabrication Rake/Gable Walls Floors Page PANEL TIP Stagger your panel placement with two panels on one side of the beam, four panels on the other side, and four back on the first side of the beam. This will help your beam stay straight Sill Plates Page Walls STEP 2. LAYOUT TRANSFER STEP 3. PANEL TILTSTEP 4. ADJACENT PANEL STEP 5. FASTENING STEP 6. TOP PLATEHeaders Page Intermediate Floors Page Roofs On the Ground Lifting PanelsPage Page Insul-Lam Electrical Where walls terminate against a panel you can drill at the horizontal electricalPlumbing Shearwalls Premier Panel R-Values Panel Core Panel Core Panel Span ft Panel Core Panel Core Panel Core Panel Core Load Chart Header Header Premier Insul-BeamIIHeader Loads Load ChartNo. of Panel Panel Minimum Speed Pressure Chart 1 ofLoad Chart 12 Wind Speed Pressure Chart 2 ofLoad Chart 12 Wind Page SOUTHWEST REGIONAL FIELD OFFICES NORTHWEST4609 70th Ave. East Fife, WA 3434 W. Papago St. Phoenix, AZ