Overview of the NAC Controller PEP Shutdown Procedure

Overview of the NAC Controller PEP Shutdown Procedure

Caution: Do not remove a NAC Controller PEP from an operating chassis system before reading the following information and instructions.

Precaución: Antes de retirar los módulos DFE del chasis en funcionamiento, lea las siguientes instrucciones y la información suministrada.

The chassis must shut down in an orderly fashion to ensure that the other devices on the network are notified of the impending change. The devices can then make intelligent decisions and stabilize the network before the change is made; thereby increasing network availability.

You can shut down a NAC Controller PEP in an operating N1 Chassis using the OFFLINE/RESET switch shown in Figure 5‐2. There are two procedures to shut down a chassis.

“Recommended Shutdown Procedure” (page 5‐7)

“Last Resort Shutdown Procedure” (page 5‐7)

Figure 5-2 OFFLINE/RESET Switch for the 2S4082-25

1OFFLINE/RESET switch

Figure 5-2 OFFLINE/RESET Switch for the 7S4280-19

1OFFLINE/RESET switch

5-6 Troubleshooting

Page 66
Image 66
Enterasys Networks 7S4280-19-SYS, 2S4082-25-SYS manual Overview of the NAC Controller PEP Shutdown Procedure