CAPACITOR

To test the field winding:

1.Connect the volt/ohmmeter probes to leads #7 and #9 where they connect to the field diode rectifier bridge. See Figure F.11.

2.Start the engine and run it at high idle (3700 RPM).

3.Check the AC voltage reading. It should be between 40 and 50 VAC.

If any one or more of the readings are missing or not within specifications, check for loose or bro-

200A

200B

ken wires between the test points and the stator windings. See the Wiring Diagram. Make sure that the windings are NOT grounded internally to the stator iron. If the leads are intact, then the stator may be faulty. Replace the stator.

If the voltage readings are within specifications, then the windings are good and functioning prop- erly.

4.If finished testing, perform the Case Cover Replacement procedure.