INSTALLATION TEST PROCEDURE
2.1.2Overall Test of CCIS Tie Line Incoming Call
STATION A’
LC |
OFFICE A
PBX |
(PBX to be tested)
OFFICE B
PBX |
STATION B’
LC |
START
Seizure of trunk to be tested
Termination of incoming call to station A’ in the self office
Check of speech
Release
When all CCIS Tie Line Trunks have been checked and a fault has been detected
END
Place the trunk to be tested into idle state, and make busy all other trunks.
An incoming call from the distant office terminates to Station A’.
After the call has been answered at Station A’, check the speech conditions including speech level, presence of noise and
Perform fault localization procedure when a fault has occurred to CCIS Tie Line. (See Procedure A of Paragraph 2.1.1)
If the distant office is faulty, make a request to the distant office for repair.
CHAPTER 5 |
|
Page 52
Issue 2