INSTALLATION TEST PROCEDURE
2.1.4Test of Tandem Connection to Tie Line
Figure 5-3 Test of Tandem Connection to Tie Line
BASIC/PRIMARY ROUTE
IRT
STATION A | PBX | TRKs |
ATTCON
(1)
(3)
(2)
PBX
TRKs |
TRKs |
PBX
ALTERNATE
ROUTE PBX
STATION B
PBX
STATION C
(1): Direct tandem connection by
(2): Tandem connection via ATTCON
(3): Tandem connection via Station
START
Test of direct
A
Test of Basic/Primary Route
Station A
calls Station
B
.
Confirm speech between Stations A
and
B
. Release.
Test of Alternate Route.
Make busy all the trunks in the primary route. Station A
calls Station
B
.
Confirm speech between Stations A
and
B
. Release.
Make idle all the trunks.
Page 55
Issue 2