INSTALLATION TEST PROCEDURE

2.1.3Test of Connection and Alternate Routing to All Tie Lines

START

Test the trunks in the primary route one at a time

Make all the trunks in the primary route busy.

Test the trunks in the alternate route one at a time.

Cancel the Make Busy condition of the trunks.

END

Make busy all trunks in the primary route except the trunk to be tested.

Station “A” calls Station “B” via the primary route.

After Station “B” answers, check the normality of the speech condition including the speech level, presence of noise, and one-way speech.

Release.

Make busy all trunks in the alternate route except the trunk to be tested.

Station “A” calls Station “B” via the alternate route.

After Station “B” answers, check the normality of the speech condition including the speech level, presence of noise, and one-way speech.

Release.

ND-71762 (E)CHAPTER 5

Page 53

Issue 2

Page 67
Image 67
NEC ND-71762(E) system manual Test of Connection and Alternate Routing to All Tie Lines