Honeywell SG-60 installation and operation guide Flash Control, Flash Feedback

Page 55

Airport Systems

3.2.2.4Flash Control

To fire the flashtube, the Digital Board pulls down the trigger request line (P2-17) for about 500uS. This signals the Trigger/High-Voltage Card to trigger the flashtube.

The Digital Board will issue its trigger request on a T2 zero-crossing. (Normally, the first zero-crossing it detects after receiving a flash request from the Master Controller.) In Day and Twilight modes, the Digital Board will issue a single trigger request. In Night mode, the Digital Board will issue a series of 15 pulses at consecutive zero crossings.

The zero crossing is determined from a 12VAC output from Flashhead transformer T2. (T2-15 and T2-16, entering the Digital Board at P2-21 and P2-23 respectively). As a failsafe measure, the Digital Board will issue a trigger request after a timeout period even if no zero crossing is detected.

When acting as a Top or Bottom Catenary Flashhead, the Digital Board will delay by 1/13 and 3/13 seconds respectively before looking for the first T2 zero-crossing, to achieve the required Catenary flash sequence:

(Middle -- 1/13 s, Top -- 2/13 s, Bottom -- 10/13 s, Middle -- etc.)

The SW2-1 and SW2-2 switches instruct the Digital Board to apply the correct timing delays for Catenary Systems. The faster flash rate (60 flashes per minute) is set by an option on the Master Controller (SW2-1).

3.2.2.5Flash Feedback

The Digital Board monitors the current discharged through the flashtube with the Flashhead current sense transformer T3. The T3 output is used to peak-charge a capacitor C17. The microcontroller reads the captured voltage level at the capacitor with A/D converter (U5) before and after the flash to determine if the flash occurred successfully. C17 will fully discharge before the next flash.

The yellow LED DS2 indicates the results of the most recent flash. If the Digital Board considered the flash successful the DS2 will be on. If the Digital Board considers the flash to have failed, DS2 will be off.

If four consecutive flashes fail, the Digital Board reports a Flash/Fail alarm to the Master Controller (per FAA specifications).

The T3 transformer connections are polarity sensitive. If the wires are reversed, the Digital Board will not be able to detect good flashes, especially in Day and Twilight modes.

3.2.3SGF-60 Trigger/High-Voltage Board

The Trigger/High-Voltage combines two completely independent functions: high voltage rectification and flashtube triggering.

SG-60 High Intensity Strobe System

3-6

Manual EPM-00000019 Rev A

Image 55
Contents Union Place Simi Valley, CA Phone 805 Fax 805 Manual Number EPM-00000019-001Approved Date Rev CommentDisclaimers Table of Contents Troubleshooting Maintenance Safety Information Qualified Personnel EPM-00000019-001 Vii Rev a General Description ScopeModel SGC-60 Master Controller Model SGF-60 Flashhead Safety Precautions Airport Systems Specifications Flashhead Fail System Configuration Configuration Switches Power ConfigurationSystem Controls Airport Systems Condition 1 You have a Catenary System Flashtube Installation Flashtube Installation Setting the Flashhead Elevation Airport Systems Master Controller Mounting Dimensions Flashhead Outline and Mounting Dimensions Typical Wiring Installation Installation WiringBlue wire Black wire PhotocellWhite wire Photocell Red wire PhotocellResponding to Top Red Beacon Failures Controlling the Red Light SystemMaster Controller TB3-C4 Master Controller TB5-NO49LCA Alarm Card NC1 9LCA Alarm Card C1Procedures for installation of conduit and tower wiring Flex Conduit Typical Installation LayoutAirport Systems Airport Systems Flex Conduit Installation Junction Box Wiring Details Flex Conduit Installation Detail WC000001 Cable Overview Splicing Details for WC000001 CableAirport Systems Airport Systems 10 Flashhead Cable 10 Master Controller Circuit Board 11 Flashhead Digital Control Board Final Installation Check Power Up and System Tests If SW2-2 is set for no External RED system OFF then If SW2-2 is set for an External RED system ON, thenDay Mode Night Mode Twilight ModeAirport Systems Airport Systems Airport Systems SGF-60 Flashhead Overall DescriptionAirport Systems Airport Systems Communications Power SuppliesMode Selection Flash Feedback Flash ControlFlashtube Triggering High Voltage RectificationSGC-60 Master Controller Airport Systems Airport Systems Master Controller Board Schematic SGF-60 Flashhead System Schematic SGF-60 Digital Board Schematic SGF-60 Trigger/High-Voltage Board Schematic Troubleshooting RLC General Troubleshooting All Flashheads Stuck in Day Mode General Troubleshooting Flashhead Does Not Flash General Troubleshooting Flashhead Stuck in Day Mode Dual System-Specific Troubleshooting Catenary System-Specific Troubleshooting Chart SGC-60 Replacement Transformer White wire to the outer bottom right terminal Flashtube Installation Ambient Light Sensor Photocell Description Part Number Replacement PartsSG-60 AOL Power Supply Component Location SG-60 AOL Flashhead Mounting Dimensions SG-60 AOL Power Supply Mounting Dimensions SG-60 AOL Wiring Installation SG-60 AOL Flashhead Component Locations SG-60 AOL Power Supply Component Locations SG-60 AOL Schematic