Protect PV.630 Installation and Start-up

Check the cables to ensure the polarity and phase sequence are correct.

Remove any cable debris, tools, bolts, etc. from the connection panel.

Replace the partition plates in the floor of the cabinet.

Reattach the connection cover.

Connection of the control and signal lines

The control and signal lines for remote signalling are connected using a 3 mm screwdriver.

Shielded control and signal lines may be advantageous in terms of EMC.

For this purpose, connect the shield of the lines to the terminal unit. Additionally, the shield can be connected to the PE con- nection provided on the control unit pivot plate.

Correct routing of the PE conductor acc. to IEC 60364-5-54.

i

6 Start-up

The cable clamp rail is located 130 mm above the floor. Observe the bending radius!

(With one bend: radius = 10 x diameter)

Special AEG Power Solutions software and hardware tools must be used for initial start-up. Only skilled personnel trained by AEG Power Solutions are in a position to use these tools correctly and to perform initial start-up.

Once the system has been fully installed, the following aspects must be checked:

Screw connections properly tightened

Connection cables correct

Tool removed

Terminal space covers attached

Read the operating instructions prior to start-up.

16 of 21

80000047963 BAL

Page 92
Image 92
AEG PV.630 manual Start-up