Section 3: Installation

Reference Manual

May 2013

00809-0100-4102, Rev AA

Five-valve Natural Gas configurations shown:

In normal operation, the two block valves between the process and instrument ports will be open, and the equalizing valves will be closed.

1.To zero the 2051, first close the block valve on the low pressure (downstream) side of the transmitter.

H

 

 

L

Test

 

 

Test

(Plugged)

 

 

(Plugged)

Equalize

Equalize

(closed)

(closed)

Isolate

 

 

Isolate

(open)

 

 

(open)

Process

Drain

Process

 

Vent

 

H

 

 

L

Test

 

 

Test

(Plugged)

 

 

(Plugged)

Equalize Equalize (closed) (closed)

Isolate

 

Isolate

(open)

 

(closed)

Process

Drain

Process

 

Vent

 

Note

Do not open the low side equalize valve before the high side equalize valve. Doing so will overpressure the transmitter.

2.

Open the equalize valve on

H

L

 

the high pressure (upstream)

 

 

 

 

side of the transmitter.

Test

Test

 

 

 

 

(Plugged)

(Plugged)

 

 

Equalize

Equalize

 

 

(open)

(closed)

Isolate

 

Isolate

(open)

 

(closed)

Process

Drain Vent

Process

 

(closed)

 

52

Installation

Page 64
Image 64
Emerson 00809-0100-4102 manual Test