Piping and Filling with Refrigerant: R-134a and R-407c Circuits

Figure 27 General arrangement air cooled Liebert XDC Lee-Temp Control

Condenser Coil

Inverted Trap * on discharge line to extend above base of coil by a minimum of 7-1/2" (190mm)

Check

Head Pressure Valve

Control with

Integral Check

Valve Lee-Temp

Receiver

Additional

Piping

Assembly **

Rotalock

Valve **

1/4" (6.4mm) Pressure Relief Valve **

Traps * every 25 ft. (7.6m) of rise on hot gas line only

Return

LiquidCondenser

from

Sight Glass

Some Models

Have 2 Sight Glasses

Standard Piping

Assembly **

Single XDC Circuit Shown

Liquid/Return

Hot Gas/Discharge

Field-Supplied Piping

Factory-Supplied Piping

*Components are not supplied by Liebert but are recommended for proper circuit operation and maintenance.

** Components supplied by Liebert and must be field-installed.

DPN000937 Pg. 4, Rev 9

Table 12 Recommended refrigerant line sizes, DX R-407c, OD copper

Liebert XDC 160

Equivalent

*Hot Gas Line,

 

Length, ft., (m)

in.

Liquid Line, in.

 

 

 

50 (15)

1-1/8

7/8

 

 

 

100 (30)

1-1/8

1-1/8

 

 

 

150 (45)

1-3/8

1-1/8

 

 

 

200 (60)

1-3/8

1-1/8

 

 

 

*Double risers are required when hot gas vertical rise is 15 feet or more (see 2.6 - Install Double Discharge Risers).