Piping and Filling with Refrigerant:
2.5.2Piping for Direct Expansion (DX)
! WARNING
Risk of refrigerant system explosion or rupture from overpressurization. Can cause death, injury and equipment damage.
Installer must install a 400 psig pressure relief valve in each of the two
For systems requiring EU CE compliance, the pressure relief valves must be
2.6Install Double Discharge Risers
For
At
The trap at the top of the riser must be tied into the top of the line to prevent oil from filling the larger riser. For each double riser used, the maximum height of the riser must not exceed 15 feet (4.6m). Multiple risers must be installed in series as the height of the hot gas line increases. Total maximum height of the hot gas line must not exceed 60 feet (18.3m).
Horizontal discharge lines should be pitched downward in the direction of flow to aid in oil drainage with downward pitch of at least 1/2 inch in 10 feet (13mm in 3m).
Figure 23 Double discharge riser layout
Connection point of upper trap is at the top of the line
Larger riser
Smaller riser is 5/8" O.D. copper
Trap size is
Contact your local Liebert representative for factory approval whenever a refrigerant piping run exceeds 200 feet (60m) equivalent length or when condensers must be installed below the level of the cooling coil.
22