Product Description
4. Move the Liebert XDC to its installation location.
! WARNING
Risk of unit falling over. Can cause death, injury and equipment damage.
The Liebert XDC is
5.Remove all lag bolts from the four (4) corner
Figure 3 Remove tie-down brackets
Unscrew lag bolts and remove brackets to release the XDC from the pallet. There are four brackets, one bracket on each corner.
6.Lift the Liebert XDC about an inch and remove the shipping pallet.
Figure 4 Remove pallet, insert piano jacks
7.Place piano jacks at either end of the Liebert XDC and lower it until it is supported by the piano jacks. Secure the Liebert XDC to the jacks (see Figure 4 for arrangement).
! CAUTION
Risk of overtightening securing strips. Can cause damage to panels.
Place a protective material between the straps of the piano jacks and the unit.
Ensure that the straps are not tightened to a point of damaging panels.
8.Back the forklift away from the Liebert XDC until the forks are no longer under the unit.
9.Using the piano jacks, maneuver the Liebert XDC into its installation