3
4. Move the Liebert XDC to its installation location.
5. Remove all lag bolts from the four (4) corner tie-down brackets. Remove the tie-down brackets
from the unit. (see Figure 3).
Figure 3 Remove tie-down brackets
6. Lift the Liebert XDC about an inch and remove the shipping pallet.
Figure 4 Remove pallet, insert piano jacks
7. Place piano jacks at either end of the Liebert XDC and lower it until it is supported by the piano
jacks. Secure the Liebert XDC to the jacks (see Figure 4 for arrangement).
8. Back the forklift away from the Liebert XDC until the forks are no longer under the unit.
9. Using the piano jacks, maneuver the Liebert XDC into its installation position—this requires at
least two people.
!
WARNING
Risk of unit falling over. Can cause death, injury and equipment damage.
The Liebert XDC is top-heavy. Use extreme caution and care when moving and installing this
unit.
!
CAUTION
Risk of overtightening securing strips. Can cause damage to panels.
Place a protective material between the straps of the piano jacks and the unit.
Ensure that the straps are not tightened to a point of damaging panels.
Unscrew lag bolts and
remove brackets to release
the XDC from the pallet.
There are four brackets, one
bracket on each corner.